OT Discovery has three installed parts: the Discovery Console for OT on a Linux virtual machine, Discovery Sensors for OT built from an ISO image, and optional OT Discovery Collectors on Windows or Linux hosts. Each Sensor is registered to the Console through a browser interface.
Plan the three components before installing anything
Each part has its own job and sizing.
| Component | Job in the deployment | Minimum resources |
|---|---|---|
| Discovery Console for OT | Command point for a network segment, or for several sites that share one flat network. Manages credentials, launches queries and forwards results through a MID Server. | 16 GB RAM, 100 GB storage, 2 CPUs |
| Discovery Sensor for OT | Runs active discovery, collects traffic and queries OT protocols such as Modbus, DNP3 and BACnet. Reports to its Console. | 2 GB RAM minimum (8 GB recommended for all queries), 100 GB storage, 2 CPUs, 2 virtual network adapters |
| OT Discovery Collector | Discovers assets from an existing host, such as a human machine interface or engineering workstation. | Windows 10 or 11 on x86_64, or Linux |
Settle the basics first: whether the devices in scope are OT or IT devices, whether the site is flat or segmented, and whether NATed or reused IP ranges exist. Place a Sensor where it can reach many devices, add Sensors behind barriers, and record zoned configurations.
Install the Discovery Console for OT on a Linux virtual machine
The Console must run before any Sensor can register. Use a minimal Linux install with an SSH server and no desktop. Set the VM’s CPU type to host so AVX and AVX2 are exposed; otherwise MongoDB can crash on restart. Allocate 16 GB of RAM and at least 100 GB of storage, more for deep packet capture, and keep 10 GB unused after installation.
- On the guided setup page, open Download & Deploy OT Discovery, select Configure, and accept the license agreement.
- Download and unzip the Console package, copy the ConsoleInstaller folder to the Linux server, and sign in over SSH.
- Run the console initialization script with sudo and accept the defaults.
- Open the Console web interface on port 8443, accept the self-signed certificate warning, and accept the license agreement.
- Create the primary local administrator, store the password securely, and enable two-factor authentication.
- Reboot the Console from the terminal.
Generate a new Console certificate before installing any Sensor, since the preloaded certificates are defaults. Upload a license ZIP containing license.pem and pubkey.pem from the Settings page. Without a valid license, Auto Query, asset scans, API token creation and collection exports are deactivated, though no data is lost.
Install the Discovery Sensor for OT from its ISO image
Download the Sensor package from the same guided setup page and unzip it. The ISO image is inside. The Sensor runs as a virtual machine on VMware, Hyper-V, Proxmox or Linux KVM, or on x86 bare metal, where a tool writes the ISO to a USB installer.
- Create a virtual machine with Other Linux 64-bit as the operating system, and attach the Sensor ISO to the CD/DVD drive.
- Add two network adapters. Components communicate when both are connected.
- Choose EFI firmware instead of BIOS, and leave Secure Boot unselected.
- Assign at least 8 GB of RAM and 60 GB of disk for the installation. To run the Sensor, size the VM to the table above.
- Power on, select Yes to start, and accept the defaults.
- When prompted, remove the install media and press a key to reboot. The Sensor screen then shows a Device Management Interface address. Record it for registration.
Register the Sensor to the Console through the Device Management Interface
The Device Management Interface (DMI) is the Sensor’s browser interface. Keep one tab on the DMI and one on the Console. Queries cannot run until registration succeeds.
- Open the DMI address and sign in with the default administrator account. The DMI then requires a new password.
- In the Console, go to Appliances, then Certificates. Under Sensor Credentials, generate a bundle and download it.
- In the DMI, go to Console, then Credentials. Choose Bundle File Input, select the bundle, and upload it. The Certificate Update Logs confirm the certificate was extracted and the Sensor registered.
- In the DMI, open the Network tab, select Edit, and enter a valid Console endpoint (IP address or hostname) and gateway. Select Save and Deploy.
- Return to the Console and select Register. The Sensor shows online briefly, then offline, then settles into a steady online status.
Install the OT Discovery Collector on Windows or Linux
A Collector runs discovery from a host already on the network. Windows installs need Windows 10 or 11 on x86_64 hardware; ARM and Apple Silicon are not supported.
Install on Linux
- On a RHEL-based system, install tar with the package manager.
- Copy the installer archive and the CollectorBundle generated on the Console to the host, then open a root shell.
- Extract the archive, then copy the CollectorBundle into the CollectorInstaller directory.
- Make Collector-init.sh executable, run it, and enter Y to accept the EULA.
- Confirm the service with systemctl status SNDiscoveryCollector, and read the journal with journalctl if troubleshooting is needed.
Install on Windows
- On the Console, go to Sensors, then Certificates. Under Bundle Password, generate a password, choose a bundle format (ZIP is recommended), and generate the bundle.
- Extract the ZIP, which holds config.json and a cert folder.
- Run the installer as administrator, accept the EULA, select the Collector install file, and select the credentials bundle.
- Select Install/Update Collector. When the window shows Installation Complete, check Program Files for the SNDiscoveryCollector folder.
Check the hostname in config.json. In offline or cloud deployments it may be wrong, and the Collector validates credentials against it, so set it to the Console’s external or network IP address.
Install containerized packages for air-gapped networks
The Console and Collector come as containerized packages, each a dependencies package plus an installer package. On a closed network, download the Console dependencies package in advance, carry it to the Rocky 10 host, and build the RabbitMQ and MongoDB images there. Run queries inside the isolated segment, download the data files from the Console to a portable USB drive, move them to a folder on the MID Server, and let the MID Server upload them to the instance.
On a Rocky 10 host, decompress the packages, run the Build the Offline Installer script, and move the resulting ZIP to the target. Install zip, Podman and the Docker engine packages, then run the script that builds the RabbitMQ and MongoDB images. Copy both archives into the OCI_compliant_images folder and run the offline Console initialization script.
Check the ports each component needs
| Port | Purpose |
|---|---|
| TCP 8443 | Console web interface and API |
| TCP 5671 | Sensor-to-Console traffic carrying data and configuration |
| TCP 5002 | Lets Sensors receive updates from the Console |
| TCP 443 | Console to the ServiceNow instance or MID Server through the connector |
| UDP 123 | Sensor time synchronization. Not needed if a time server or hypervisor provides the time |
Choose a deployment layout that fits the network
In a flat network, components reach each other directly, so one Console can serve several sites and extra Sensors speed up discovery. Segmented sites split the network into zones with no traffic between them, so each zone gets its own Console, Sensors and Collectors. Micro-segmented sites combine several segments, each with a Console and at least one Sensor. Deploy a separate MID Server for each network or segment, with firewall rules across each boundary.
Restart a Collector after a configuration change or a fault
Manual restarts apply to Windows Collectors and to Linux systemd agents, after a configuration refresh or when a Collector is unstable.
On Linux, run the restart command as root or with sudo:
systemctl restart SNDiscoveryCollectors
On Windows, open the Services dialog, select SNDiscoveryCollectors, and choose Restart the service. The restart command uses the plural service name, while the status and journal commands use the singular.
Deregister a Sensor or remove a lost one
In the Console, go to the Sensors page, select the Sensor, open its Actions icon, and choose Deregister Device. In the confirmation window, select Deregister. The Sensor resets to DHCP with a link-local fallback.
To remove a Sensor that has stopped responding, open its record on the Appliances page, select the Action button, and choose Remove Device from Console. That option appears when the status is Connection Lost. If the Sensor is linked to a site, a warning says the removal cannot be undone. Continue, then select Remove Sensor. Its network connections stay in the system for records. Power the unit down and remove it from the field, since it can keep running. Reinstalling it later means the vendor’s technical support team must reconfigure it. Removal can involve dangerous voltages, so trained staff should handle it.
Frequently asked questions
Can I register a Sensor before the Console is installed?
No. Registration needs a running Console and a credentials bundle generated from it.
Do Collectors need DMI registration?
No. Once the installer completes, the Collector appears in the Console.
Why does the Sensor show online, then offline, after I select Register?
The Console shows the Sensor online briefly, then offline, before it settles into steady online. Wait for steady online before running queries.
What happens to discovery if the Console license expires?
Auto Query, asset scans, API token creation and collection export are deactivated. No data is lost, and a valid license restores them.