Simplified Change Management is configured in the Configuration Console, where four change models set how each change type is handled, scheduled and communicated. Activating the ITSM Change Management Admin Experience plugin makes the simplified models the active defaults and deactivates the classic global models, except a customized classic Normal or Emergency model. Blackout and maintenance schedules then decide when changes may be implemented.
The four change models define how each change type is handled
Simplified Change Management includes four configurable change models, and each fits a different kind of change. Normal covers planned work that passes through a risk assessment, approvals and a post-implementation review. Standard covers pre-approved, low-risk changes that repeat. They bypass the full approval workflow and start from approved templates. Emergency is a fast-track route for urgent work, with limits on who can submit and a notification when one is created. Change Registration records changes controlled by an external team or vendor, such as a platform upgrade carried out by an outside party. It has no approval workflow.
| Model | Typical change | Approval workflow | Access and notification settings |
|---|---|---|---|
| Normal | Planned change needing risk assessment | Assess and Authorize states, set per risk level | Availability toggle and templates |
| Standard | Pre-approved, repeatable change | None; bypasses the approval workflow | Templates listed in the New section |
| Emergency | Urgent change | Authorize state, set per risk level | Submitter groups and email recipients |
| Change Registration | Change made outside the standard workflow | None | Registrant groups and email recipients |
Activating the plugin changes the default models
Activating the ITSM Change Management Admin Experience plugin, which carries the sn_itsm_chg_admin identifier, makes the simplified Normal and Emergency models the active defaults on the change creation page. The simplified Change Registration model becomes active and visible too. The classic global Normal, Emergency and Change Registration models are deactivated and hidden.
Two checks come before relying on the new defaults. A classic global Normal or Emergency model that was already customized is left exactly as it is, so its settings are not overwritten, and the plugin does not deactivate it. The Standard, Unauthorized, Cloud and Cloud Infrastructure models keep their current behaviour, and the simplified Change Registration model keeps working as before.
The plugin also tightens Standard change records. Short description, description, risk, impact, justification, assignment group, planned start date and planned end date become required fields, and work notes become read-only for anyone without the Change Manager role. Do not adjust the defaults by hand, because the models function as an interdependent set.
Configuring the Normal model’s availability, approvals and tasks
Open the Normal model from the Change models list in the Configuration Console. The Available for new change requests toggle controls whether it appears in the change type picker. Turning it on sets the matching global model to inactive and points the ITIL changes process at the simplified model. The New section lists the templates that use the model, and each one pre-fills common fields and follows the model’s workflow and approval requirements.
Assess and Authorize carry the approvals, and each is set separately for low, moderate and high risk. Assess confirms that documentation is complete and the change is ready for authorization. Authorize is the business gate that confirms a change may move into implementation. Both offer the same five approver choices. Member of assignment group lets any member approve, and one approval is enough. Manager of assignment group requires that group’s manager. Change manager lets any member of the change management group approve. CAB member requires at least one Change Advisory Board member. Other group requires approval from a group you select.
By default, Assess uses assignment group membership at all three risk levels. Authorize uses assignment group membership for low risk and a CAB member for moderate and high risk. Both can be changed to match how approvals run in your organization.
Scheduled, Implement and Review each carry a Yes setting that creates a change task when the change enters that state. Scheduled checks planning and resources before implementation. Implement carries the change through execution, verification and documentation. Review confirms the change succeeded and records lessons learned.
Standard, Emergency and Change Registration models set access and notifications
Standard changes are selected from templates, not from the change type picker. The Standard model holds no availability, approval or automatic task settings, because Standard changes bypass approval. Its job is managing the template list in the New section.
The Emergency model’s New state names the users or groups who may submit emergency changes. Only members of those groups can choose the model. Emergency changes skip normal scheduling, so keep the list short and limited to teams that can authorize urgent work. Selectable users must hold the sn_change_write role. An email goes to the configured recipients each time an emergency change is created. Emergency’s Authorize state uses the same approver choices and defaults as Normal, and its Scheduled, Implement and Review states carry the same task controls.
Change Registration has no approval workflow. Under who can register external changes, you select the users or groups allowed to choose the model. Limiting registration to change managers or team leads who coordinate with external parties keeps the model with the people who manage those relationships. Under who should be informed, you add recipients and an email template, and each registration sends them an email.
Building templates that link requests to a model
A template standardizes a common change request so that people do not build it by hand. It can be created for the Normal, Standard or Emergency model, or for a custom model, and it inherits that model’s approvals and state transitions. Because of that inheritance, the approval path does not have to be rebuilt inside each template.
Preset fields fill in default values on each new request. Field policies make a field mandatory, optional or read-only, and a read-only field displays only its predetermined default. Child task templates can be added in the Change Task Template tab, each with its own fields and field policies.
Publishing moves a template from Draft to Proposed, and a proposed template cannot be modified, so review it fully first. If no approvers are configured for the template, it moves to Published by default. An active published template is usable immediately. The Active checkbox is ticked by default, and clearing it keeps the template unavailable after publication.
Blackout and maintenance schedules control when changes run
Schedules are reached under ITSM fulfiller experience, then Change Management, then Change schedules. The list has Blackouts and Maintenance tabs, and some schedules are pre-configured. Select Add New to create one, or open an existing schedule to edit it.
A blackout blocks changes during critical periods, such as a financial year-end or a major platform release. A maintenance window names the periods when changes are expected, such as a recurring patching cycle. Both serve as the authoritative source for downstream enforcement, including conflict detection and approval routing. The schedule name appears in the change calendar, conflict notifications and audit reports, so state the type, scope and timeframe, such as a regional holiday blackout or a monthly patching window for one region.
Scope has three options. All CIs covers all configuration items in the database. CI class covers a class such as all Windows servers. Change request applies by attributes such as assignment group, change model or change type. Pick the narrowest scope that still captures the risk.
Set a start and end date and time, or choose All day, and select the time zone. Repeat can be One time, Weekly, Monthly, Yearly or Specific, where the Repeat every field sets a custom interval. Save stores the schedule, and Mark as configured completes the step. Undo reverts unsaved changes from the current session. The schedules step can also be completed through the Configure with AI conversational flow in the banner at the top of the page. A saved schedule is active immediately and used for conflict detection and change enforcement, so check the time zone and recurrence before saving.
Prerequisites, roles and finishing the setup
Make sure the groups, assignment groups and notification recipients you plan to use already exist before you start, because each model’s approver and recipient fields draw on them.
Each section is controlled by a child role under the Change Management Setup Administrator role, sn_itsm_chg_admin.admin. Models need sn_itsm_chg_admin.change_models_config (or the admin role), and schedules need sn_itsm_chg_admin.change_schedules_config. The parent role uses a dotted suffix (sn_itsm_chg_admin.admin) and the child roles use an underscore suffix (sn_itsm_chg_admin.change_models_config and sn_itsm_chg_admin.change_schedules_config). The model and schedule roles no longer inherit sn_ia_config.ia_user automatically, so that role must be assigned explicitly alongside the Change Management role. Existing roles are not changed during an upgrade, so anyone relying on inherited access cannot configure the console until the role is assigned.
When all required models are configured, select Mark as configured on the Configuration Console to complete the change model step. An optional Advanced configuration section offers further settings.
Frequently asked questions
What changes the default model for new requests?
Activating the ITSM Change Management Admin Experience plugin. The simplified Normal and Emergency models become the defaults, and the classic global models are deactivated unless a classic model was already customized, in which case it stays as it is.
Why can a user not configure the console after an upgrade?
The model and schedule roles no longer inherit sn_ia_config.ia_user, so that role must be assigned explicitly alongside the Change Management role.
Who can submit an emergency change?
Only members of the users or groups named in the New state, and only users holding the sn_change_write role can be selected for that list. The configured recipients receive an email each time an emergency change is created.
Are schedules enforced as soon as they are saved?
Yes. A saved schedule is active immediately and used for conflict detection and change enforcement. A blackout blocks changes in its window, while a maintenance window marks when changes are expected.