OBLYTECH Logo
OBLYTECH Logo

Mock Load Reconciliation for Salesforce Migrations

A mock load reconciliation compares record counts and key totals between the source system and the Salesforce target after each rehearsal load. The point is to find which field mappings, lookups and transformations fail before the production cutover, while there is still time to correct the mapping spec and rerun the load.

What the reconciliation proves and what it does not

A rehearsal load answers one question: can the data move from the legacy system into the new org without losing or distorting records? Row counts alone cannot answer it. A load can hit the expected number of rows while all accounts point to the wrong owner, or while a currency field is blank on half the opportunities. The reconciliation is the set of checks that turns a rehearsal into evidence.

Treat the pack as a gate, not a report. Each rehearsal produces a reconciliation pack, the team reviews it, and the result decides whether the next rehearsal runs with the same scope or with corrected mappings. A pack that is filed without a decision has not done its job.

Set up source and target counts before the first rehearsal

Agree the object list and the population for each object before anyone runs a load. The population is the set of records the migration scope selects, such as active accounts, open cases from the last three years, or contacts linked to a retained account. If the source extract and the target expectation use different filters, each later comparison will show differences that nobody can explain.

Write the expected count for each object as a query against the source, not as a figure typed into a spreadsheet. Save the query text with the pack. When a number changes between rehearsals, the team can see whether the data changed or the filter did.

Counting parents and children separately

Count parent records and child records on their own, then count the children again through their parents. A contact load can show the right number of contacts while a third of them are attached to no account. Include a count of child records without a valid parent in the target. A failed parent lookup can pass through a load without stopping it, so the load log alone may not show the gap.

Compare key totals as well as row counts

Row counts catch missing records. Key totals catch wrong records. Pick a small set of numeric and date fields per object, such as order amount, quantity, start date and close date, and total them on both sides. Add grouped totals too: amount by owner, by region or by year. A grouped total that is off by a small amount usually points to a mapping or a rounding rule.

A reconciliation for one object usually includes these checks:

  • Record count, split by the population filter
  • Sum of each agreed currency or quantity field
  • Count of blank values in each required field, on both sides
  • Count of records per owner and per record type
  • Count of child records without a valid parent in the target

Grouped totals by owner often feed account reporting, so a mismatch there reaches account teams quickly. Business owners should review those totals first. Teams that report on account health often need the same owner figures, and the customer success manager account health views in Salesforce page is a related starting point for that reporting.

Map each source field to an expected target result

A reconciliation can point to a mapping when each source field has a written target. Build a mapping register with four columns: the source field, the target field, the transformation rule and the expected value for a sample record. After each rehearsal, pull a sample of target records and compare them against that expected value by hand. Ten to twenty records per object is a workable sample size for a rehearsal. Include the awkward cases: blank fields, long text, records that came from a merged account, and records created by an integration.

Keep transformation rules short and testable. “Join first name and last name with one space” can be checked. “Clean up names” cannot. If a rule needs a paragraph to explain it, split it into two rules or move the logic into the source extract, where the team can review it before the load.

Lookups and legacy identifiers

Each parent reference in the target needs a source identifier that survives the load. Store the legacy identifier in a field the team can query after cutover. The reconciliation can then match records on that identifier instead of on name, which is the dependable match when two accounts share a name. Lead owner fields are a common case where the rule depends on assignment logic, so the migration team should read the marketing operations lead assignment rules and handoff checks page alongside the register before writing the owner rule.

Decide which mismatches block cutover

Sort each difference into one of three groups before the review meeting. Blocking differences stop the cutover. Examples include a missing population, a total that is off on a field used for revenue or compliance reporting, or a lookup that points to the wrong parent. Accepted differences are known, explained and documented, such as duplicates removed under an agreed rule. Deferred differences affect records the business can correct after go-live, and each one has an owner and a date.

Write the decision next to the difference, not in a separate summary. A reviewer should be able to read one row and see the object, the expected value, the actual value, the group and the owner. A difference with no owner tends to stay open through cutover, and then it becomes a support ticket.

Run the reconciliation after each rehearsal, in the same order

Consistency between rehearsals matters more than speed. Run the same checks in the same sequence each time, so that a change between runs tells you something about the data or the rules. A sequence that holds up across rehearsals looks like this:

  1. Freeze the source extract and record its timestamp and record count.
  2. Run the load into the rehearsal target and save the load log.
  3. Compare record counts for each object against its expected population.
  4. Compare key totals and grouped totals, applying the agreed tolerance.
  5. Sample target records and check them against the mapping register.
  6. Classify each difference as blocking, accepted or deferred.
  7. Record the decision and owner in the pack, then decide whether the next rehearsal repeats the same scope.

Freezing the source extract is the step teams skip. If the source keeps changing during the rehearsal, a count mismatch could be new data rather than a broken mapping. Use a fixed extract. If the legacy system must stay live, record the delta separately so it can be explained in the pack.

Assigning roles for each check

Assign roles check by check. The data owner signs off on populations and accepted differences. The migration analyst runs the queries and assembles the pack. The technical lead signs off on load logs and failed-record handling. The business owner for each object signs off on the grouped totals that drive reporting. When one person holds all of these roles, the review tends to confirm what that person already expects. A second reviewer who checks the sample is the simplest fix.

Teams without an in-house migration analyst can look at the dedicated Salesforce delivery teams option for that role.

For help planning this work, see Salesforce implementation.

Common failure points in rehearsal reconciliations

The same few problems recur across rehearsal cycles.

Counts that match for the wrong reason

A load can match the expected count because a filter in the extract dropped the same number of records the target was meant to receive. Check that the population definition is identical on both sides. Sample the excluded records as well as the included ones, since an excluded record that should have loaded is a blocking difference even when the count agrees.

Totals that move between rehearsals

If a grouped total changes between two rehearsals with no mapping change, look at currency conversion dates, time zone handling on date fields, and rounding in the transformation rule. The fix is usually in the rule rather than in the data.

Defaults that hide blanks

A default value applied during the load can fill a required field and hide the gap in the counts. Count blanks in the source and the target separately, and treat a default value as a difference to be explained, not as a pass.

Questions about mock load reconciliation in migration rehearsals

Who owns the pack when the migration team and the business disagree?

The migration lead owns the pack, but the business owner for each object decides what counts as a blocking difference. Escalate the specific row, not the whole pack, and record the decision with the name of the person who made it.

How should the schedule account for reconciliation time?

Build the schedule backward from the review meeting, not forward from the load window. Teams often find that the checks take longer than the load itself, especially when a rule change forces the grouped totals to be recounted.

What happens when a fix to one mismatch breaks another?

Treat the change as a new rehearsal scope and rerun the full reconciliation, not just the check that failed. A change to one transformation can move totals for other objects that share the same field. Keep the previous pack so the two runs can be compared line by line.

Does a clean reconciliation mean the data is ready for cutover?

It means the rehearsal data matched the expectations written down before the load. Readiness also depends on whether those expectations covered the right population and whether accepted differences were agreed with the people who use the data. A clean pack built on thin expectations gives false confidence.