A cutover freeze and delta load plan splits one migration into two passes. The bulk load copies the main body of records from an extract taken while the source stays live. The delta load then moves the records changed after that extract, during a short freeze on source edits. Freeze length depends on how well you capture those changes.
Why the bulk load and the delta load need separate jobs
The bulk load is the heavy move. Teams pull the full population of records for each in-scope object, transform them, and load them into the target. On a large dataset that run takes hours, and users can keep working in the source while it runs. The delta load is a much smaller run. It takes the records that changed after the extract was pulled and applies those changes to the target, which lets it fit inside a freeze that users will accept.
Without the split, the freeze has to cover the whole bulk run, and users wait through the longest part of the migration with edits blocked. Separating the two passes moves the long work outside the freeze, so the freeze holds just the short work.
The split carries a risk of its own. Each change made after the extract has to be found reliably. Weak change capture lets the delta miss records, and the target goes stale without anyone noticing. Name the change detection method in the plan before anyone agrees on a freeze time.
Setting the extract boundary and the freeze start
Fix the extract boundary first. Record the exact moment the extract starts, in the time zone both systems use, and treat that value as the line between the two passes. Anything modified before the line belongs to the bulk load. Anything modified after it belongs to the delta. Use one value across all in-scope objects so that a parent and its children are not split across different cutoffs.
If the source clock differs from the host that pulls the extract, widen the delta selection by a few minutes. Rows that overlap are safe to reapply, because the identifier map matches them to existing target records. Missing rows are not safe.
Open the freeze after the bulk load has passed its validation counts, not when the bulk run starts. The freeze begins just before the delta extract and ends once the delta is applied and checked. A freeze opened at the start of the bulk run turns a short cutover into a long outage, which is a common planning error.
Set the freeze length from a timed dry run against a copy of the source with a realistic change volume. Time each step and add margin for reconciliation. A length estimated from the size of the organization alone tends to be wrong.
For help planning this work, see Salesforce implementation.
Running the bulk load while the source stays live
The bulk load reads from the extract, so users keep working during it. Keep the extract scope exact. The object list, filters and field set should match the mapping sheet line for line, because a filter that differs between the extract and the delta is a frequent cause of records that fail to reach the target.
Choose the loading method by volume and by how much rework a failed batch creates. Methods differ in error reporting, batch sizing and logging. The trade-offs are set out in choosing Salesforce data loader options for migration, which is worth reading before the runbook fixes the method for each object.
Load in dependency order. Parent records such as accounts go first, followed by children such as contacts and opportunities. Keep a map from source identifiers to target identifiers for each object. The delta relies on that map to update existing target records rather than create duplicates, so store it where the delta process can read it.
Record rows attempted, rows loaded, rows rejected and the reason for each rejection. That rejection list is the worklist for any cleanup that must finish before the delta.
Building the delta load and its change capture
The delta needs a definition of “changed” that the team agrees on. A source modification timestamp compared against the boundary is the usual starting point. Records created after the boundary and records edited after it both belong in the delta. Deleted records are a separate decision: remove them, archive them or leave them in place, and write that choice into the runbook.
Test change capture on a small sample before the rehearsal. Edit a few records in each object after the boundary, run the selection, and confirm each edit appears once. A missing edit usually points to a filter problem, and a duplicated edit usually points to a join that multiplies rows across child records.
Apply the delta as updates where the identifier map has a match and as inserts where it does not. Name the match key for each object in the runbook. A wrong key creates duplicates during the freeze, and those are harder to unwind once users return.
Move work out of the freeze. Fix formats, complete required fields and resolve known duplicates before the extract, following the sequence in data quality work for Salesforce migrations.
Sequencing the freeze, the delta and the go-live checks
A single cutover window usually follows this order. Use it as the runbook skeleton and fill in the timings from the rehearsal.
- Confirm the bulk load passed its validation counts and that the rejection list is closed or formally accepted.
- Announce the freeze and confirm that users have stopped editing the in-scope objects.
- Pull the delta extract at the agreed boundary and record row counts by object.
- Apply the delta in dependency order using the identifier map.
- Run the reconciliation checks below, then run a few business transactions with a named tester.
- Lift the freeze after the business owner signs off the reconciliation result.
Write the rollback decision point into the runbook as a fixed time before the freeze lifts. After users return and enter new edits, reversing the cutover means reconciling changes in two directions, which is slow and error-prone.
Roles and decisions to settle before the freeze
Name one person who owns the freeze decision. That is usually a business owner, because the freeze stops work for teams outside the migration. The migration lead owns the runbook. Each in-scope object needs a data owner who signs off its reconciliation counts. The administrator who runs the load and the delta needs write access for the cutover window, and that access should be removed when the window closes.
Put these decisions in writing before the rehearsal:
- The extract boundary and its time zone.
- The freeze start, the freeze end and who announces each.
- Which objects are frozen and which stay open for reading.
- How deletes and merges during the freeze are handled.
- Who approves a rollback, and the time by which that approval is due.
Teams short on people who know the source data often feel this gap at this stage. A dedicated Salesforce delivery team is one structure some organizations use for the technical run. The freeze decision and the reconciliation sign-off still belong to the business.
Reconciliation checks after the delta load
Reconciliation shows that the target matches the source when the freeze lifts. Start with counts. For each in-scope object, compare source and target totals for records created, updated and excluded. A gap that matches known rejections can be explained. An unexplained gap stops the cutover.
Then sample records from each object, weighted toward records edited during the freeze, and compare key fields one by one. Include parent and child relationships, because a correct parent with a broken child link passes a count check and still fails in use.
Check for duplicates in the target using the matching rules the business approved. The Salesforce data steward duplicate review routine explains how to work through candidates and keep an audit trail. Duplicates that appear after the delta usually trace back to the match key, so review the identifier map before merging anything.
Record each check with the time and the signer’s name. That record is what the business relies on when a question about a migrated record arises after go-live.
Questions about freeze timing, delta scope and cleanup
Can report owners use figures from the source during the freeze?
They can, but those figures describe the state before the delta lands. Ask report owners to label any number pulled during the freeze as provisional and to rerun it after reconciliation. Figures that drive payments or commitments should wait for the signed reconciliation.
What happens when a record is edited in the target during the freeze?
Treat it as an incident, since the target should be closed to business users for the freeze. Capture the record, decide which version is correct, and apply that value through the delta process so the identifier map and audit trail stay intact.
Does each object need its own delta run?
Usually not. One boundary value can drive a single delta run that processes objects in dependency order. Separate runs make sense when one object has a much larger change volume, so it can be scheduled on its own.
What if the delta overruns the freeze window?
Set a cut-off time for the delta run in the runbook. If it passes, the rollback approver chooses between extending the freeze and reverting. The engineer running the job reports progress against the cut-off, and the decision sits with the approver.
Should fixes found during the freeze go into the cutover?
Fixes that block a load go in. Other fixes go to a backlog for after go-live, because each change made during the freeze must be reconciled and tested again.