Basic Software Records in Software Asset Management

ServiceNow basic software records let you follow installed software through discovery models, purchased software profiles, and license entitlements before reviewing compliance. In Basic Software Asset Management, start with the discovered identity, complete manual normalization where needed, check the licensing relationships, and reconcile the appropriate publishers. A compliance total becomes more useful when you can explain the records behind it.

Understand the ServiceNow basic software record relationships

A software model describes purchased software, including its publisher, version, and discovery map. An entitlement connects that profile with purchased rights and records the license terms. Multiple entitlements can belong to a single software model. Neither record replaces the evidence of what discovery found on a device.

Installation records reside in Software Installations [cmdb_sam_sw_install]. Each installation references a discovery model representing the discovered software. Several discovery models can relate to one software model: different discovered versions can satisfy the version criteria of the same purchased software profile. This distinction matters when investigating why separate installation identities contribute to one licensing position.

Use the record type to frame your question. An installation describes software found in the environment. A discovery model supplies the identity used for normalization. The software model describes the purchased configuration, while the entitlement supplies its rights. As a recommended review method, follow these relationships for one product before assessing a larger publisher portfolio.

This page covers Basic Software Asset Management behavior in Brazil. The guide to Software Asset Management Professional covers the neighboring product scope. Keep that distinction clear when choosing which workflow to assess.

Check how installations enter the review

Installation data can arrive through SCCM integration or ServiceNow Discovery. For the Discovery route, Request Discovery must be activated. When an installation is written, a business rule examines the discovered publisher, product, and version. An existing matching discovery model receives the installation reference; otherwise, the system creates a discovery model and links the installation to it.

Discovery models are generated by discovery rather than created manually. Their matching key consists of Publisher, Display Name, and Version. The installation form also exposes the referenced discovery model and the hardware in Installed on. For an unexpected grouping, a useful investigation is to compare the installation values with the referenced model instead of judging the relationship from a product name alone.

SQL Server, Exchange Server, and Oracle Database have patterns already used by Basic Software Asset Management. Additional patterns require configuration. A sam_admin can configure the pattern’s pre/post processing and select software under Sync Installed Software, then create a Software Installation Name Mapping record containing the pattern class, publisher, and product. This allows discovered records from that pattern to populate the installation table for reconciliation.

As a planning recommendation, establish whether collection already covers the required application before adding a pattern. If an edition was not discovered, the installation’s Edition Override field can hold a known edition. Record why that value is known; an override should express an established identity rather than a guess made to obtain a different result.

Normalize the identity before interpreting license rights

Discovery models distinguish New from Manually Normalized. New indicates that manual normalization has not happened. Completing key identity fields manually produces Manually Normalized. These labels concern the model’s normalization state; they do not, by themselves, answer whether purchased rights cover the installations.

Product type also affects reconciliation. Only discovery models classified as Licensable are considered. Other available types include Child, Driver, Not Licensable, Patch, and Unknown. An Unknown type can be changed, and changing the product type updates the normalization status to Manually Normalized. Check this field when explaining why a discovered model participates in a compliance calculation.

Version matching first seeks an exact value. If that fails, matching can fall back to the major version when selecting the software model. For review, distinguish the discovered full version from the version criterion used by the purchased software profile.

Use the Software Library when identifying a product. If the product is absent, a sam_admin can add a custom software product through All > Software Asset > Administration > Custom Software Products. The custom record’s publisher and product combination participates in discovery model normalization. This route supports homegrown software as well as products not yet represented in the library.

The custom product form includes product type, product classification, and an Active setting alongside publisher and product. A missing publisher can be created through the Publisher field’s Companies lookup. As a review recommendation, first establish that the required product is absent, then document the identity chosen for the custom record. Creating another name for an existing product would leave the original identification question unanswered.

After identity review, inspect the software model and its entitlements together. Keep questions about license terms distinct from questions about discovered values. The license metrics, suites, and custom metrics guide provides a separate route for that licensing discussion.

For help planning this work, see ServiceNow implementation.

Choose the reconciliation scope and interface

Reconciliation produces compliance results by comparing discovery with entitlements. The default schedule recalculates positions weekly. Manual runs let you choose individual publishers or the full publisher set between scheduled runs. Selecting fewer publishers can shorten processing and gives an initial review a more manageable set of records.

Use the workspace controls

Workspace reconciliation accepts sam_user or sam_admin. It covers products that have software entitlements or software installations. Open Software asset > Software asset workspace > Run Reconciliation, or reach the same dialog through Software Asset Workspace > License workbench > Run Reconciliation.

Choose the publisher scope, then decide whether organizational grouping is useful. Country, Department, Company, Region, and Cost Center are available for both grouping and subgrouping; None leaves that selection ungrouped. Select Run Reconciliation and wait for processing to finish. Completed results appear in the Reconciliation tab.

As a working recommendation, note the selected scope before starting. A department-level run and an ungrouped publisher run answer different review questions. Retaining those choices makes it easier to interpret a later comparison without assuming that a changed total must reflect changed software consumption.

Use the classic action with its own requirements

The classic action requires sam_admin and reconciles products with entitlements. Go to All > Software Asset > Reconciliation > Run Reconciliation, choose the publisher selection, and select Continue. The Reconciliation Results list appears after processing. Allow for the run to finish before interpreting its outcome.

The two interfaces therefore have different documented role and product eligibility requirements. Assign the review to someone with access to the intended action. The roles and responsibility planning guide can support that ownership decision.

Read the run details and then investigate remediation

In workspace, Number identifies the run, Last reconciled gives its reconciliation date, and Ran for identifies the publisher scope. Publishers appears when particular publishers were chosen. Group and Subgroup retain the organizational selections. Check these details before comparing the result with another run.

Status distinguishes Completed, In Progress, and Failed. Progress supplies a percentage and bar. For more detail, personalize the list to add Progress summary, which describes the processing step and is initially hidden. A visible run record is therefore not enough to establish that processing has completed.

Users with sam_user can inspect reconciliation results. The License usage screen sits under Software asset > Software Asset Workspace > License usage. It offers domain and compliance filters, access to reconciliation, information about the latest run, and report viewing and export. To prioritize a review, choose whether the ordering should emphasize true-up expense, excess licensing, or possible savings.

The remediation labels distinguish several positions: rights not in use and rights not allocated appear alongside rights needed, reclaimable rights, and unlicensed rights. Use the relevant label to identify the issue being investigated, then inspect its supporting records. As a recommended acceptance practice, retain the run number, scope, reviewed inputs, and owner of the proposed response.

The testing and acceptance checklist provides a place to plan that review. Ask a second reviewer to trace the selected result through its installation, normalized identity, and licensing records. This is a suggested validation method, not another platform prerequisite.

What if Discovery predates Basic Software Asset Management?

Previously discovered installations may need migration after Basic Software Asset Management is installed. A sam_admin can open All > Software Asset > Administration > Migrate Software Installs to copy earlier records into [cmdb_sam_sw_install]. Allow the operation to complete before checking the Software Installations list.

The script is unnecessary if Discovery was used with an earlier ITSM Software Asset Management version. It is disabled when the destination already contains installation records; running Discovery again can repopulate that table. Check those conditions before treating migration as a required setup step for every environment.