Set up the client-side planning console

If every date change you make in the planning console is saved to the server at once, a planner can lose the flow of a session while the recalculation runs. Client side planning holds those edits in the browser until you choose to save them. To enable it, a pps_admin configures the project planning context and its business-rule prerequisite. Plan around the actions that require an immediate server save before you continue.

This option sits under the legacy planning console, so confirm which console your instance uses before you configure it.

Understand what changes during a planning session

A project schedule contains connected decisions. Moving one task can change the dates of dependent tasks and the project. Creating a task or adding a dependency can also require dates to be recalculated. If each interaction is saved to the server, the wait for those operations can interrupt a planner who is still working through the structure.

With client side planning enabled, these changes remain in the browser until the user explicitly saves. This reduces the repeated server interactions associated with building the schedule. The distinction is between the working plan currently visible in the console and the changes committed to the server. A visible date change is therefore not enough to establish that the revised plan has been saved.

Use this mode when your planning session involves related structural changes that you want to review together. For example, you might adjust a task date, inspect the effect on its dependents, and reconsider the sequence before saving. Treat that as a working schedule until you choose to commit it.

Enable the client side planning console

The role required to enable client side planning is pps_admin. Arrange for the person making this configuration change to have that role. The pps_admin role is the role required for this setup step.

  1. Check the project property Enable firing of Business Rules on save from Planning Console. It must be set to false before the client-side option can be enabled.
  2. Navigate to All > Project Administration > Settings > Planning Console.
  3. In the Planning Console list, expand Context: default.
  4. Select Project[pm_project].
  5. Select the Enable Client Side Planning check box.

Confirm the labels and behavior on your instance and release before applying the change to working projects. Record the previous property value and planning-context setting so that the configuration owner can explain what changed. The property prerequisite deserves review with whoever maintains scheduling customizations, because enabling the console option involves an explicit choice about business-rule behavior.

Keep the configuration decision tied to the planning problem. Describe the lag you are trying to remove, the sequence of edits that exposes it, and the projects used for validation. For a wider review of planning priorities, see the IT strategy and planning support page to frame the decision before changing several planning practices at once.

Build a schedule around deliberate save points

Start a validation session with a small, understood task structure. Note the original dates and dependency relationships. Change one task date, then inspect the affected dependent tasks and the overall project dates. The purpose is to check both the schedule result and the distinction between browser-held work and a committed plan.

Next, try a sequence representative of the planner’s normal work. Add a task or a dependency, inspect the recalculated dates, and review whether the structure expresses the intended sequence. Save explicitly when the changes form a coherent planning decision. Do not use the absence of visible lag as the criterion for accepting the schedule; the dates and relationships still need review.

If the revised structure raises staffing questions, separate that review from the browser scheduling check. The related resource management in PPM guidance addresses the adjacent resource-planning subject. A schedule that recalculates quickly still needs people available to perform the work.

Recognize actions that require saving first

Client side planning includes exceptions where you must save changes to the server before proceeding. Build these boundaries into the work sequence so a planner does not arrive at an exception while still deciding whether to keep earlier changes.

  • Create baseline
  • Copy project
  • Copy partial project
  • Add child tasks
  • Add external dependency
  • Edit Assigned to
  • Edit Additional Assignees

For example, review your current schedule edits before creating a baseline. If the task sequence is still under discussion, finish that discussion before saving and proceeding. Similarly, distinguish ordinary dependency work from adding an external dependency, which is explicitly included among the save exceptions.

Assignment edits also need attention. A planner moving between task sequencing and named assignees can encounter a server-save boundary even though the session still feels like one planning exercise. Group the work thoughtfully: review the structural changes, save them, then proceed with the assignment action. Do not assume that enabling browser-side scheduling makes those assignment changes part of an uninterrupted unsaved sequence.

Columns with custom business rules enabled are additional exceptions. Include them in the local planning instructions alongside the named actions. A checklist that lists the standard exceptions but omits customized columns will leave planners with an incomplete account of when saving is necessary.

Work through the related console tasks in a planning session

Most sessions start with the structure itself. Open the project planning console, create a parent-child relationship for each group of tasks, and then add the dependencies that tie one task to the next. These are the operations where the lag described earlier tends to show up, because a new task or dependency can delay the display of its dates until the server has responded. In browser-side mode those dates update within the session, and the server receives them when you save.

Predecessor dependencies deserve their own check. The planning console reference treats them as a separate topic. Use the Gantt chart for an overview, then review the predecessor entries when you decide whether a dependency is correct.

Custom columns need their own review. Any column with custom business rules enabled is treated as an exception, so an edit there can force a server save even when the rest of the session stays in the browser. List those columns before the session starts and test them one at a time, as the validation steps below describe. The related topic on custom columns in the planning console is the place to confirm which columns carry those rules.

  • Check the dependent task dates after each date change before you make the next one.
  • Review the predecessor entries for every task whose dependencies you added or changed.
  • Note which exception actions appear in the sequence before you save the session.
  • Confirm that the project property Enable firing of Business Rules on save from Planning Console is still set to false after any configuration change.

Validate customizations and investigate remaining delays

If enabling the option is blocked, begin with the stated prerequisite: Enable firing of Business Rules on save from Planning Console must be false. Check that value before making unrelated configuration changes. Also confirm that you are editing the intended Project[pm_project] entry under Context: default.

If planners still notice pauses, identify the exact action involved. Was it a task date adjustment, an explicit save, an assignment edit, or an action involving a customized column? That distinction matters because the feature reduces immediate server posting for planning changes while retaining save requirements for the exceptions.

Test custom columns individually. Record which columns have custom business rules enabled and include an example edit for each in the validation session. Compare the observed sequence with the expected save boundary. Avoid changing several rules at once while investigating; a narrower test makes it easier to explain which configuration affected the planner’s experience.

For help planning this work, see ServiceNow implementation.

Keep a short acceptance record covering the configuration, the tested planning sequence, the recalculated dates, the explicit save, and the exception actions exercised. Give the planner and configuration owner the same record. This provides a concrete basis for deciding whether the setup is ready for routine planning.

Use the console within the project’s planning boundaries

Browser-side scheduling answers how a planner develops the task structure without saving each interaction. It does not decide which business commitments belong in that structure. Bring those commitments into the review before accepting the revised dates, particularly where another team depends on the timing.

For projects involving service recovery, connect schedule assumptions with RPO and RTO planning. Those recovery objectives provide a separate planning input. Keep the acceptance question specific: does the saved project structure support the agreed work sequence and timing? Faster interaction helps the planner examine alternatives, while that review determines whether the selected alternative is suitable.