A ServiceNow timeline visualization is a planning view that lays change requests, projects and other ITSM activities out across time, by month in 2D or in lanes in 3D. On Xanadu and Zurich, ServiceNow no longer deploys, enhances or supports the feature, and on Yokohama it is being prepared for future deprecation while remaining supported. Check your instance release before setting a deadline.
What a timeline visualization shows
A timeline visualization is a picture of an organization’s activities over time, used to judge the effect of upcoming change requests and projects before they land. Administrators could build views for incidents, problems, changes and projects.
The feature came in two layouts. The 2D view groups activities by month, stacks the panels for each month in date order and can be printed from the browser. The 3D view groups activities into lanes and moves along a time slider.
Lanes, panels, markers and the slider
A lane is a logical grouping of items in the 3D view. One lane might hold pending projects while another holds open projects. A visualization can show up to eight lanes at a time, and the Settings pane lets a viewer hide or show individual lanes. A marker is a horizontal line that crosses the lanes and signals the start of the next month.
A panel is the block that represents an item record. In 2D a panel represents a single record. In 3D a panel can represent one record or several. On the CIO Roadmap, projects that share a planned completion date merge into one 3D panel, whose header turns black when it stands for more than one project. In 2D those projects stay as separate panels.
The slider sets the period on screen. In 3D you drag the slider along the slider track; in 2D you drag the slider track itself. The track also gives a second view of the data, because a coloured dot marks a day with one or more items. A dot does not equal one panel, so the track helps you find a period of interest rather than count records.
Clicking a panel opens a summary window, and clicking its heading opens the full record. Shift-clicking a single-record panel opens the full record directly.
Activating the feature and who can use it
An administrator switches the feature on by activating the Timeline Visualization plugin, identified as com.snc.timeline_visualization. The path is All, then System Applications, then All Available Applications, then All. The administrator finds the plugin by name or ID and selects Install. If domain separation and delegated admin are enabled, the administrator must be working in the global domain, or the installation stops with a message that another plugin activation is running.
Activation adds two tables, one for visualizations and one for each viewer’s personal settings, along with a UI policy, client scripts and a business rule that checks for an existing default when a second visualization is set as the default. Activating the plugin does not switch on the predefined CIO Roadmap, which also needs the Project Portfolio Management plugin, com.snc.financial_planning_pmo.
Two roles control access. The timeline_admin role creates and edits visualization pages and views them, and it includes the timeline_user role. The timeline_user role views visualizations, and users with the project_manager and project_user roles also receive it. Avoid granting the broad admin role when a more specialized role covers the need.
Building a visualization
Timeline administrators create a visualization from Timeline Visualization, then Create New. Plan first: choose the table, the fields, and the filters and sorting. Viewers can personalize their copy, so narrow filters can hide categories people expect. The CIO Roadmap is a reasonable starting point.
The core settings are these.
| Setting | What it controls | Default or limit |
|---|---|---|
| Name | Unique name for the visualization | Must be unique |
| Panel table | Records shown as lanes and panels | Tables and database views in the same scope |
| Relationship field | Field whose values become lane titles | Usually a reference field or a limited set of values |
| Show slider | Displays the date slider | Checkbox |
| Panel name | Field shown in the panel body | Taken from the panel table |
| Panel date | Date value that places each panel on a lane | Date and date-time fields |
| Default | Marks the visualization applications use | One default per table |
| Max items per lane | Items shown in a 3D lane | 500, hidden until added to the form |
| Max items per lane 2d | Items shown in a 2D lane | 99, hidden until added to the form |
The Panel date needs careful setup, because it decides where each item appears. In 3D it sits in the panel header, and in 2D in the panel body.
Filtering and sorting
The lane condition filters and sorts the values used as lanes in 3D. Setting Name is not IT removes the IT lane from the visualization and from the lane options in the Settings pane, and removing the filter brings it back. The same builder sorts values: sorting Name z to a lists portfolio names in reverse alphabetical order on the CIO Roadmap.
The panel condition filters and sorts the items shown as panels in 2D and 3D. A panel condition of State is one of Pending, Open and Work in Progress keeps projects in those three states on the timeline and leaves other states off it.
Colour coding and labels
Colour is driven by one field from the panel table, the panel color key. Its values populate the label fields. The CIO Roadmap uses State, which carries the values Pending, Open, Work in Progress, Closed Complete, Closed Incomplete and Closed Skipped. Other fields that suit this role include Priority, Risk and Approval.
Up to four values can receive their own colour. Label 1 through Label 4 each take one value, and Color 1 through Color 4 set the colour for the label in the same position. If Label 1 is Pending and Color 1 is red, pending projects appear red. Values without a label use the default colour.
Setting the summary view
Each table can have one timeline visualization view, which decides which record fields appear in the pop-up summary when a panel is clicked. To create one, open a record on the table, right-click the form header, and choose Configure, then Form Layout. Under Form view and section, set View name to New, enter timeline visualization, and confirm. Add or remove fields with the Available and Selected columns, then save.
Without one, panels show the fields from the table’s default form view. Once it exists, all panels for that table use it. An incident view might show the incident number, priority and short description.
Personalizing a view
Viewers personalize from the Settings pane by selecting Configure. The form offers the same conditions, colour key, labels and colours that administrators set, and changes apply to that viewer’s view.
The Settings pane also holds the Key, a View switch between 2D and 3D, a View list option that opens the full record list in a new tab, and a Portfolio control for adding or removing lanes. In 2D, a Show all button overrides the lane filters from setup.
To open a visualization for projects, go to Project, then Projects, then All, scroll to the bottom of the list and select the Timeline Visualization related link. The CIO Roadmap opens in 3D with the current date at the front. For other applications, open the application navigator, select All, and look for the related link, which appears when a visualization exists for that table.
Opening a visualization marks it as personalized, so the viewer keeps their own version when the administrator later changes the default. Setting Max items per lane above 1000 may delay timeline data in Internet Explorer.
Support status and the migration path
On Xanadu and Zurich, ServiceNow no longer deploys, enhances or supports timeline visualization, so teams on those releases should plan a move. On Yokohama it will be hidden and no longer activated on new instances, but it remains supported, so teams on that release should plan ahead. Note the release version on your instance before setting a deadline. Standard customers install the Portfolio Planning application and Pro customers install the Strategic Planning application, both from the ServiceNow Store. The Portfolio Planning Workspace (SPM Standard) is the migration target for this functionality, and it sits in Strategic Portfolio Management.
For roadmap and portfolio work on this site, see the strategic portfolio management guide and the project portfolio management guide. Plan the move before the feature is retired from your instance, and use the Strategic Portfolio Management guides linked above for the current setup.
This page does not cover timeline pages, which show record information over time, or the History Timeline, which compares configuration item snapshots.
Frequently asked questions
Is ServiceNow timeline visualization still supported?
On Xanadu and Zurich it is no longer deployed, enhanced or supported. On Yokohama it is being prepared for future deprecation but is still supported. Check your instance release before setting a deadline.
Who can set up a timeline visualization?
Users with the timeline_admin role can create and edit visualizations. Users with the timeline_admin or timeline_user role can personalize one from the Settings pane.
What is the difference between a lane and a panel?
A lane is a grouping of items in the 3D view. A panel is the block that represents one record in 2D, or one or more records in 3D.
Why does the CIO Roadmap not appear after I activate the plugin?
Activating timeline visualization does not switch on the predefined CIO Roadmap. That roadmap also needs the Project Portfolio Management plugin, com.snc.financial_planning_pmo.
Does the summary window show all fields of a record?
Not by default. It shows the fields from the table’s default form view, unless a view has been created for that table.