OBLYTECH Logo
OBLYTECH Logo

Business Continuity Plan Exercises

A business continuity plan in ServiceNow connects recovery scope, owners, teams, dependencies, and tasks in one record. Exercises test whether those arrangements work under disruption. Link the gaps discovered during testing to plans and exercises as issues, then use evidence from follow-up tests to decide whether the recovery approach needs revision.

Build a business continuity plan in ServiceNow around a testable outcome

Start with the service or business activity that must continue, rather than a document outline. Define the disruption, the acceptable operating level, and the recovery decision the exercise should test. A plan covering a payment process needs different participants and evidence from a plan covering loss of a workplace.

To create a plan, use the sn_bcm.program_manager or sn_bcm.planner role. Navigate to Workspaces > Business Continuity Workspace > Planning in the list view and select New. Complete the Details tab, including Name, Template, Type, Business Unit, Department, and Expires as appropriate. Saving the plan creates it in Draft.

Assign a Plan owner, Plan owner group, or both. The creator is the default individual owner. Group members have the same plan edit rights as the owner, so choose a group whose membership reflects responsibility for maintaining the recovery approach. For the plan owner group filter, the roles are sn_bcp.plan_contributor or sn_bcp.plan_manager.

Before scheduling a test, agree who can change the plan and who can accept the outcome. An exercise facilitator can collect observations without being the person authorized to approve a revised recovery approach. For the broader application context, see the guide to ServiceNow Business Continuity Management.

Check scope and recovery targets before the exercise

The Scope tab connects assets to the plan. It includes recovery objectives, recovery tier, and a BIA reference. When a dependency is added, finalized recovery time objective and recovery point objective values come from the latest business impact analysis. If the BIA changes afterward, select Update dependencies to retrieve the updated values.

Refresh the page after the dependency update completes and review the resulting relationships. The Asset dependencies tab shows relationships between assets. An asset can be both a primary scope and a related asset. These distinctions matter when the exercise tests a shared dependency supporting several business activities.

Compare the plan’s scope with the proposed scenario before inviting participants. Ask whether a supplier, application, facility, or upstream service could prevent the recovery sequence from starting. Treat an absent dependency as a planning gap to investigate, rather than assuming the asset is outside the exercise because it is missing from the record.

  • Confirm which business activity and assets are included in the test.
  • Check that recovery objectives reflect the BIA used for the exercise.
  • Identify dependencies participants will simulate and those they will actually test.
  • Record the assumptions that could change the interpretation of the result.

Check the screens and capabilities on your instance and release before following this workflow; application versions can affect ownership, recovery teams, and workspace layout. Where technical restoration supports the business outcome, coordinate with disaster recovery planning so the business test and restoration test use compatible assumptions.

Turn recovery tasks into an exercise sequence

In Documentation, describe the recovery capabilities that participants need to understand. Use Loss scenarios to describe the disruption being addressed, and Recovery teams to connect responsibility to the plan. Keep operational instructions specific enough that another qualified team member can follow them without relying on the author’s memory.

Recovery tasks include Planned order, Short description, Owner, Dependencies, Planned duration, Phase, and Asset recovery level. Task dependencies determine the sequence, while independent tasks can run in parallel. Review the dependency chain as well as the displayed order: an apparently early task may still depend on work that has not finished.

For exercise preparation, walk through one complete route from disruption to the agreed operating level. Ask who starts each task, what input is needed, and what proves completion. Check for circular dependencies, including a plan being triggered again through a chain of related work. Resolve these during planning rather than discovering them during the timed test.

A suggested scenario is a business application remaining unavailable while its supporting infrastructure appears healthy. Ask the team to explain how it would continue the business process, obtain missing information, and decide whether to use an alternative procedure. This tests coordination and decision points alongside technical activity.

Use the exercise and event task guide for the neighboring task execution workflow. Keep this plan review focused on whether the intended recovery approach is clear enough to test.

Capture observations that explain the result

Prepare an observation sheet before the exercise. As a working method, capture the expected action, observed action, affected asset, elapsed time, and supporting evidence. Separate the participant’s explanation from what the observer could verify. This prevents a confident verbal account from replacing evidence of a working recovery step.

During a discussion exercise, a participant may describe how a task would be completed without executing it. Label that result as a discussion outcome in your exercise notes. A successful conversation does not demonstrate that access, data, equipment, or a third party will be available during disruption.

When a task takes longer than planned, investigate the cause before changing the target. The delay might come from an unavailable approver, an incorrect dependency, or instructions that leave a decision unresolved. Updating a duration without explaining the cause can make the next test appear improved while the operational problem remains.

At the debrief, distinguish actions completed, actions simulated, and actions blocked. Identify which findings require a plan change and which require work elsewhere. Give the plan owner a concise account of what failed, why it matters to continuity, and what a successful retest would demonstrate.

Track exercise gaps through linked issues

The Issues related list on plans, recovery events, and exercises supports creating an issue or associating an existing issue. Issue integration depends on the installed GRC applications, including GRC: Profiles, GRC: Issue Management, and GRC: Advanced Core for issue triage. Check those dependencies if the expected list is missing.

For plan issues, sn_bcp.plan_contributor, sn_bcp.plan_manager, and sn_bcm.program_manager provide read, write, and create access. For recovery events and exercises, sn_recovery.event_manager and sn_recovery.event_user provide those issue permissions. The sn_bcp.plan_viewer role provides read access. Adding or creating an issue also requires write access to the plan, and the record must allow editing.

An issue created from a plan receives the Business continuity management classification and identifies that plan as its primary source. Additional linked plans or events become secondary sources. Use an existing issue when a shared failure affects several plans, rather than creating separate records that obscure the common cause.

Write the finding so a remediation owner can act on it. For example, describe a recovery task blocked by missing access, name the affected plan and exercise, and specify the evidence needed to demonstrate correction. Agree responsibility, a review point, and a retest condition through your issue management process.

For help planning this work, see ServiceNow implementation.

Revise the plan and verify the correction

Use the issue review to decide what must change: ownership, documentation, recovery tasks, dependencies, or the recovery strategy itself. Avoid treating issue resolution and plan approval as interchangeable decisions. A completed access request may fix one obstacle while the recovery sequence still needs another test.

Compare the retest against the original failure condition. Keep the evidence narrow enough to support a clear conclusion: the team obtained the required access, completed the blocked task, and produced the agreed output. If a broader exercise is needed to demonstrate the business outcome, record that remaining work explicitly.

Review the revised plan through its configured approval workflow. Plans move through review and approval before Approved, with Archived used later in the lifecycle. Give reviewers the material changes and the evidence supporting them, so approval reflects an understood recovery approach.

Questions about continuity exercise records

Does removing an issue from a plan delete it?

No. Removing the association from the related list leaves the issue record intact. Check other linked plans and events before removing a relationship, because another team may still need the finding.

Can findings be added to an archived exercise?

Issues cannot be added or created when the plan, recovery event, or exercise is in a state that prevents editing, such as Archived. Arrange the findings review before archiving the exercise.

Does copying a plan reset its ownership?

A copied plan retains the original Plan owner and Plan owner group. Review those values before using the copy for a different department or recovery team, so responsibility does not remain with the wrong people.

Where can reviewers obtain an offline plan copy?

The plan supports More actions > Generate PDF and More actions > Generate MS Word. Review the generated report before using it in an exercise, especially where participants need ownership and issue details alongside the recovery instructions.