To set up stories and epics in ServiceNow Agile Development 2.0, create an epic for the larger requirement, then create stories under the same product. Select each story’s Epic and Release, assign its team, and define acceptance criteria. Check dependencies and task ownership before treating the stories as ready for sprint planning.
Plan the story, epic, and release relationships
Start with the outcome you intend to deliver. Use an epic to hold the larger requirement and stories to describe work that the team can develop and test. A release association on a story identifies its intended delivery grouping. Decide these relationships before entering a batch of records.
Product is a key setup field. The story’s Epic choices come from epics associated with its Product. Its Release choices come from releases associated with that product. A story belongs to one epic at a time, while an epic can contain multiple stories. Agree on the product before troubleshooting an apparently missing epic or release.
For example, a team might group improvements to request intake under one epic, with separate stories for validation and confirmation messages. Give each story its own acceptance criteria and select its intended release. This makes the relationship explicit without putting the entire requirement into one difficult-to-test story.
The steps below use Brazil behavior; check form availability and customizations on your instance and release. For the surrounding planning concepts, see the ServiceNow Agile Development guide.
Create an epic with a clear boundary
Epic creation lists the roles scrum_story_creator, scrum_admin. Navigate to Agile Development > Epics and select New. Complete Product, Priority, State, Short Description, and Description as appropriate, then click Submit. Write the description around the requirement and its boundaries so that later stories have a clear reason to belong.
An epic can be associated with one product at a time. Choose that product deliberately rather than using a broad epic name to group unrelated products. If the requirement needs further breakdown, select New in the Child Epics related list. To create a story within the epic, select New in its Stories related list.
Use Ready when the epic is ready for the product team to break down. Work in Progress represents development on its stories. Complete represents completed development and testing across the stories and child epics. Treat those meanings as review criteria when agreeing how the team will maintain the epic.
Identify what belongs in this delivery and what should remain separate. A clear boundary helps reviewers distinguish missing work from an unrelated request that happens to use the same application.
Create stories and link them to releases
Story creation lists the roles scrum_story_creator, scrum_admin. Navigate to All > Agile Development > Stories and select New. You can also start from the Stories related list on a product, release, sprint, theme, or epic. Some fields may already contain values because of that starting context, so inspect them before submitting.
- Select Product, then choose the matching Epic. Select Theme if the story should also belong to a theme associated with that product.
- Set Release to the intended release associated with the selected product. Check the actual selection rather than assuming the epic establishes the story’s release.
- Select Assignment group for the Agile team. Sprint becomes available when Assignment group has a value. Choose the sprint when the team has agreed its scheduling.
- Complete Short description, Description, and Acceptance criteria. Use Type to distinguish work such as Development, Documentation, or Spike.
- Enter Points for estimated effort and Priority for planning. Review State, which defaults to Draft, and select Submit.
The saved story reopens with related links and lists. Reopen the relevant records and verify Product, Epic, Release, and Assignment group together. A correct description does not compensate for selecting a different delivery release. Check the saved relationships on a representative story before repeating the setup for the rest.
Write acceptance criteria as observable outcomes. For the validation story, specify what a user enters, what the application should accept or reject, and the result a tester should observe. Keep implementation notes in the description where they support the requirement. Avoid using a task list as a substitute for acceptance criteria.
The story appears in the backlog according to the populated fields. Continue with ServiceNow backlog planning when the relationships are correct and the team needs to rank the resulting work.
For help planning this setup, see ServiceNow implementation.
Add dependencies before committing delivery order
Dependency editing lists the roles scrum_story_creator, scrum_story_editor. Open the story through All > Agile Development > Stories. Use Prerequisite Stories for stories that need to finish before the current story, and Dependent Stories for stories that rely on the current story finishing. Select Save and then Update.
For the request-intake example, a confirmation-message story might depend on validation work being complete. Review that relationship from both sides: which story must finish first, and which story is waiting for it? This review helps catch a reversed dependency before the team schedules work around it.
The scrum program board can display these relationships at All > Agile Development > Agile Board > Program > Planning. Use the dependencies icon to show or hide the connections. Access to this board requires the Scrum Programs plugin, com.snc.sdlc.scrum_program.
Review dependency order alongside the selected releases. If prerequisite work is planned later than its dependent work, resolve the delivery sequence with the teams involved. For record or board problems that remain after these checks, use the Agile Development troubleshooting guide.
Break stories into owned scrum tasks
Creating scrum tasks lists the roles scrum_story_creator, scrum_admin. Open a story, select New in the Scrum tasks related list, complete the task fields, and select Submit. The task’s Story field identifies its parent story. Assignment group is populated from that story, and Assigned to defaults to the story owner; review ownership before work begins.
Use Planned hours for the estimate, Remaining hours for work still needed, and Actual hours for the completed effort. Add a specific Short description and Description so the assignee understands the work. A new task defaults to Draft. Use Blocked and Work notes to make an impediment and its context visible.
To create a batch, right-click a story number and choose Add Scrum Tasks. Enter quantities for Analysis, Coding, Documentation, and Testing, then select OK. These records begin with the short description ToDo… . Open them afterward and replace that starting text with meaningful descriptions, priorities, and ownership details.
Creating a Scrum Task under a Story makes the story’s date fields read-only. Check the story’s scheduling information before creating tasks. A story is not complete until its tasks are complete, so review unfinished tasks when the story appears ready to close.
Run a small setup review before expanding the backlog
Use one epic and a small set of stories to review the setup with the people who will maintain it. Confirm that the epic describes the intended requirement, the stories have testable outcomes, and each story points to the intended product and release. Ask the team to explain the dependency order without relying on story names alone.
Then inspect task ownership and estimates. Distinguish an unestimated story from an intentionally small story; the epic exposes Missing estimate to help identify gaps. Review completion information with the product owner before using it in a delivery conversation, especially when work varies substantially in size.
Keep a short acceptance record of the review: the epic and story numbers, the selected release, unresolved sequencing decisions, and the person responsible for each correction. Expand the setup after those corrections are checked. This gives the team a concrete pattern to repeat without multiplying incomplete records.
Questions about story and epic setup edge cases
Why do epic completion percentages differ?
Percent complete by count uses story counts, while Percent complete by epic uses story estimates. Several small completed stories can therefore produce a different view from the estimate-based measure when a larger story remains unfinished. Choose the measure that answers the delivery question being discussed.
Can I duplicate a story without retyping it?
Insert and Insert and Stay are available through story additional actions when glide.ui.task.insert and glide.ui.advance are true. Insert and Stay leaves the new story open for editing. These actions are unavailable for stories added from the triage board. Review inherited details before using the copy.
Does Classification connect a story to a defect?
Classification defaults to Feature and has no connection to the Defect and Enhancement fields in Related Records. Use the appropriate reference there for the associated record. Opening defects or enhancements requires feature_user, which the administrator grants to the users expected to open them.
Why is a project phase already selected?
Project phase becomes available after Project is selected. When that project has one phase, the story is automatically tagged to it. An agile phase can contain stories belonging to more than one group, so review the story’s team assignment separately.