SAFe and Agile 2.0 Dashboards in Performance Analytics Packs

The SAFe and Agile 2.0 content packs for Performance Analytics add ready-made dashboards for feature, epic, sprint, program increment, release and team progress. Each dashboard has its own indicators, charts and widgets. Trend charts also need a daily data collection job, and a trend can only use data gathered after that job starts.

Installing the packs and checking access

The Essential SAFe pack is installed as a store solution. An administrator opens System Applications, searches the ServiceNow Store for the pack name and follows the store steps. The Agile 2.0 pack is installed the same way under its own name. Some dashboards in both packs are inactive by default and must be activated before end users can see them.

Unlimited access to the features of the Essential SAFe solution needs a Performance Analytics subscription, and using the solution needs an active subscription to Performance Analytics for Business Management. The Agile 2.0 pack carries the same subscription requirement.

Two business stakeholder roles give read access: sn_safe_read for Essential SAFe and sn_agile_read for Agile 2.0. For general background, see reporting and dashboards.

Check this before building on the packs. Six related plugins are being prepared for future deprecation, including Portfolio SAFe, Essential SAFe, Work Progress Status for SAFe and the Essential SAFe content pack itself. Under that change the listed plugins are hidden and cannot be activated on new instances, although they remain supported. Enterprise Agile Planning in Strategic Planning is named as the newer experience.

Turning on daily data collection

Trend dashboards depend on a scheduled job. For background, see the scheduled job explainer. In the Essential SAFe pack it is named “[SAFe] Daily Data Collection”; in the Agile 2.0 pack it is named “[Scrum] Daily Data Collection”. Both sit under Performance Analytics, then Data Collector, then Jobs.

The person creating the job needs the pa_admin or admin role. The Run as field needs a user holding pa_admin, pa_data_collector or admin. The Run As tz field sets the time zone used for database queries and for indicator conditions such as “created today”, so check that it suits your organization. Scheduled runs start when the Active checkbox is ticked and the record is saved with Update.

Historical data collection is not supported for the indicators behind either job, so a trend can only use data gathered after the job starts. Switch the job on before the first sprint you want to report on.

Essential SAFe dashboards: feature, epic and sprint views

Feature and epic dashboards

The Feature dashboard shows scope change and story progress for one feature over a period. Its widgets are Stories, Scope in story points, Stories Missing Estimates and Blocked Work. Its charts are Stories By State, a bar chart; Feature Burnup, a line chart; and Story Cycle Time, a bubble chart.

In the bubble chart, bubble height is the number of days a story took from in progress to completion, and bubble size is its relative story points. Hovering reveals the completion date, total cycle days and days spent in Work in progress, Ready for testing and Testing. The story state panel narrows the chart to chosen states and shows their combined duration.

The Feature Burnup has four series: Scope, Scope Forecast, Completed and Completed Forecast. The point where Completed Forecast crosses Scope Forecast is a predictor of when the feature might be completed. If the two lines do not meet, scope is growing faster than finished work.

The Epic dashboard applies the same logic to an epic. Its charts are Feature Progress, a horizontal bar chart with one bar per feature; Epic Burnup; an Epic Cumulative Flow Diagram; and a Story Cycle Time bubble chart. The flow diagram tracks stories from Work in Progress through Ready for Testing and Testing to Complete; stories in the Ready and Cancelled states are left out of it. For background on epics, see the epic explainer.

Sprint and prior sprint dashboards

The Sprint dashboard tracks the current sprint and forecasts where it will finish. It shows Scope, Percent Completed, Time Elapsed, Blocked Work and Stories Missing Estimates. Committed Points is not visible by default and must be added from Reports.

The Sprint Burndown compares remaining work with an ideal line. Remaining work above the line means the sprint is behind schedule; below the line means it is ahead. Cancelled stories are excluded from this dashboard’s data.

The Prior Sprint dashboard looks back at the previous sprint, showing committed points, stories completed, points completed and stories still missing estimates, with a Sprint Burndown and Sprint Burnup for that sprint. For the wider agile measures behind sprint reporting, see agile development KPIs and metrics.

Program increment and ART dashboards

The PI dashboard follows feature progress inside the current program increment. Its widgets are Scope, Percent Completed, Time Elapsed, Features, Features Released, Stories Missing Estimates and Blocked Work. Its charts are PI Burndown, PI Burnup, PI Feature Progress, Velocity by Sprint, a PI Cumulative Flow Diagram and a Story Cycle Time bubble chart.

The ART dashboard has three tabs. ART Summary shows Feature Progress across the agile release train and Velocity by PI. Cycle Time shows the bubble chart. Program Predictability plots business value achieved per completed PI as a percentage, for the ART and for each team. A band from 80% to 100% marks the ideal range for hitting PI objectives consistently.

Team dashboard

The Essential SAFe team dashboard covers story progress, velocity, capacity and team members. Work item progress shows Active Stories By State, Time in State and Average Cycle Time per State. Sprint Performance holds Velocity History, which covers the past 10 sprints and plots team capacity, committed points, completed points, average completed points and a linear trend. Sprint Variance expresses completed work against capacity and against commitment.

Velocity by Type is a stacked bar chart separating regular stories from stories added to the unified backlog from triage board items. It is not on the dashboard by default and must be added from Scrum custom charts. Story Cycle Time on this tab counts stories completed in the past 30 days.

Agile 2.0 dashboards: sprint, epic, release and team views

The Agile 2.0 dashboards sit under All, then Agile Development, then Dashboards.

The Agile 2.0 Sprint dashboard reports Percent Completed by Points: completed story points in the sprint divided by all sprint story points, multiplied by 100. Its widgets are Scope, Percent Completed, Time Elapsed, Committed Points, Missing Estimates and Blocked Work. Committed Points is hidden by default and can be added from Reports. Its charts are a Sprint Burndown, a Sprint Burnup and a Sprint Cumulative Flow Diagram. Reports here filter on the sprint’s planned end date, so a completed sprint appears once that date is today or earlier. The Prior Sprint dashboard shows committed points, stories completed and missing estimates for the previous sprint.

The Epic dashboard uses Total Story Count, Stories Completed and Missing Estimates as widgets, with an Epic Burnup, an Epic Cumulative Flow Diagram and a Story Cycle Time bubble chart. The Release dashboard reports Percent Completed, Scope, Time Elapsed and Blocked Work.

The Agile 2.0 Team dashboard uses four tabs: Work item progress, Sprint Performance, Team Members and Cycle Time. Work item progress shows Active Stories by State, Time in State in hours per state and Average Cycle Time per State. Sprint Performance holds Velocity History, Velocity by Type and Sprint Variance over the past 10 sprints. Story Cycle Time counts stories finished in the past 30 days.

Upgrading an existing dashboard layout

Essential SAFe users on pack version 1.1 can install the latest dashboard layout from Solution Library. Users upgrading from version 1.0.1 or earlier should install the Feature, Sprint, PI, Epic and Team dashboards from there. Agile 2.0 users on version 1.1 can install the latest layout the same way, and users on 1.0.2 or earlier should install the Epic, Sprint, Prior Sprint, Release and Team dashboards.

Each install adds specific charts. For example, the Essential SAFe Epic dashboard gains an Epic Burnup, an Epic Cumulative Flow Diagram and a Story Cycle Time chart, and the Agile 2.0 Team dashboard gains Velocity History, Velocity by Type, Sprint Variance and Story Cycle Time.

On the Brazil release (Essential SAFe) and the Paris release (Agile 2.0), the Install and Upgrade buttons may be missing from the Solution Library content form.

After an upgrade, the team member list can appear on both the Work item progress tab and the Team Members tab of the team dashboard, and one of the two copies is accurate. Removing the widget from the Work item progress tab avoids the duplicate on the Essential SAFe team dashboard.

Changing indicators, UI scripts and story states

Indicators come first. A user with the admin or pa_admin role opens Performance Analytics, then Indicators, then Automated Indicators, opens the indicator, edits its Additional conditions and clicks Update. The Essential SAFe example adjusts the sum of story points of a feature’s stories for the current sprint, which drives the Burnup report.

UI scripts come second. An admin goes to System UI, then UI Scripts, opens the script, overwrites the base implementation and clicks Update. For the SAFe Sprint Cumulative Flow Diagram the script is SAFeAreaChartImpl; the Agile 2.0 customization topic names ScrumAreaChartImpl as an example of an area chart UI script to override.

Story states come third. Adding a state changes what the reports count, so indicators that read the State field must be updated as well. A user with the admin or pa_admin role opens a story under Scaled Agile Framework (SAFe), or under Agile Development for Agile 2.0, right-clicks State, chooses Configure Choices, enters a New item name and a numeric value, clicks Add and then Save. For background on stories, see the story explainer.

Frequently asked questions

Why does a new dashboard show no history for earlier sprints?

Historical data collection is not supported for the indicators behind the job, so trend history only starts once the job is running.

Which role is needed to see the dashboards?

Essential SAFe dashboards check for safe_scrum_user, and Agile 2.0 dashboards check for scrum_user. Business stakeholders with read access can use sn_safe_read for Essential SAFe or sn_agile_read for Agile 2.0.

What does the point where the forecast lines meet tell me?

On the Feature Burnup, the point where Completed Forecast crosses Scope Forecast gives an estimate, based on historical data, of when the feature might be completed. If the two forecast lines do not meet, scope is increasing faster than work is finishing.

Can the duplicate team member list be removed?

Yes. Remove the widget from the Work item progress tab; the Team Members tab keeps the accurate list.