Scrum Programs in Agile Development: Create, Plan and Staff

A scrum program in Agile Development lets several scrum teams plan their sprints against one shared view. You create the program under the it_program_manager role, assign teams that already exist as agile groups, build an epic backlog to filter the work, add sprints for each team, and then drag stories into those sprints on the program planning board.

Work out the setup order before you open any forms

The steps depend on each other. The program needs its teams, each team must exist as an agile group before it can be assigned, and planning needs both a program and an epic backlog. Each step names its own required role, so check the role before you start it. If you are still deciding how programs fit a SAFe or EAP setup, the scaled agile planning overview covers that first.

Step Action Role required Starting point
1 Create an agile group for each team admin All > Agile Development > Create Agile Group
2 Create the scrum program it_program_manager Agile Development > Scrum Programs > New
3 Build the epic backlog it_program_manager Agile Development > Epic Backlogs > New
4 Assign teams to the program it_program_manager Teams related list on the program record
5 Add sprints for each team scrum_sprint_planner Agile Board, Program tab, Planning
6 Plan stories into sprints scrum_sprint_planner Agile Board, Program tab, Planning

Create the program record

There are two ways into the program form. The Scrum Programs module is the standard route: select Agile Development > Scrum Programs, then New. The board offers a shortcut from Agile Development > Agile Board, where you open the Program tab, select Planning and click Create Program. That shortcut works only for your first scrum program, so later programs must be created from the module.

Field What to enter Default or behavior
Planned start date The day the program starts, typed in or picked from the calendar The current day
Planned end date The day the program ends Entered by you
Planned duration Days and hours Filled in from the start and end dates. The default duration is one day
Program manager The person who manages the program Entered by you
Default Epic Backlog The initial epic backlog for the planning page Not applied automatically on the planning page, so select the backlog manually while planning
Program Name A brief description of the program Entered by you

Submit the form when the fields are complete.

Assign teams to the program

Teams are attached from the program record. Open the program, find the Teams related list, and click Edit. Move the teams you want from the Collection list to the Teams List, then click Save. The added teams then appear in that program’s Teams related list. A team can be added to more than one scrum program by following the same procedure.

Each team must exist first as an agile group, meaning an assignment group of the type Agile Team. The form asks for a name and a description that can list the products or releases the group works on.

Build epic backlogs to filter the planning work

An epic backlog is a saved set of filter conditions over epics. When you plan, you can show only the stories that belong to the epics in one backlog. For example, you might create a backlog of epics whose Priority is High, then plan sprints around those epics first.

The default filter on a new backlog is Task type is Epic and Active is true. Add more conditions with Add Filter Condition, or add a second group with Add OR Clause. Enter a name, set the conditions and click Submit. You can create the backlog from the Epic Backlogs module or from the Backlog tab on the Agile Board. On the board, the first backlog is created with Create Backlog and later ones with the create icon.

On the Backlog tab, the Backlog list switches between backlogs, and Create Epic adds a new epic to the one you are viewing. Editing the backlog definition requires the it_program_manager role. Epics can be reordered by priority by dragging, or from the keyboard. The more options icon offers Move to top, Move to bottom and Product.

Add sprints for each team

Sprints are created per team from the planning board. Open the Program tab, select Planning, choose the program from the Program list, and click Add sprints under the team’s name. The Create Sprints form has five fields.

Field Purpose
Name The name of the sprint for this team
Starting Number The number the sequence begins with. Enter 1 for a team’s first sprint
Start date The start date of the team’s sprint
Duration (days) The length of each sprint for this team
Number of Sprints How many sprints to create in one action. Enter 4 to add four sprints

The new sprints appear under the team on the planning board. Pointing at a sprint name shows its duration, total story points and filled capacity, and clicking it lets you edit the group capacity and planned dates.

Plan stories on the program planning board

The planning board is where the program is scheduled. Go to Agile Development > Agile Board, open the Program tab, select Planning and choose the program. The board shows the teams, their sprint cadences and their capacities. Choose an epic backlog from the Backlog list, click the backlog icon to show its epics, and select an epic to see its stories.

To assign a story, drag its card from the backlog into a sprint or into a team’s backlog lane. Stories and their priorities are covered in the backlog guide. The drop changes the story’s references as follows.

Action on the story Assignment group Sprint
Dropped into a sprint Updated to that team Updated to that sprint
Dropped into a team’s backlog lane Updated to that team Not changed by this action
Moved from a sprint to a team’s backlog lane Kept Cleared
Dropped back into the epic backlog pane Cleared Cleared

The sprint capacity bar under each sprint name fills as stories are scheduled into it.

Component What it does
Program selector Switches programs. The edit icon adds teams or changes program information
Configuration panel Turns the team backlog lane and story dependency lines on or off
Epic Backlog pane Lists the matching epics with their unassigned and unscheduled stories
Scrum teams panel Lists the teams. Clicking a team name edits its members, group capacity or description
Sprint workload capacity bar Compares the workload planned for a sprint with the team’s capacity

With the Agile Development Unified Backlog plugin (com.snc.sdlc.agile.multi_task) active, the board also shows stories added from the triage board.

Read story dependencies on the board

Open a story from Agile Development > Stories, or from the program board. In the Prerequisite Stories related list, add the stories that must finish before this one. In the Dependent Stories related list, add the stories that rely on it. Select Save, then Update. Adding dependencies requires the scrum_story_creator or scrum_story_editor role.

On the board, the dependencies icon in the configuration panel shows or hides the dependency lines. Green means the prerequisite is scheduled in an earlier sprint than the dependent story. Red means the dependent story was placed in a sprint before its prerequisite, so review it and reschedule as needed. If no story on the board has a dependency, the option does not appear.

Roles, installed components and board limits

Activating the Scrum Programs plugin installs the roles, tables, business rules and UI macros the program uses. The it_program_manager role gives full control over all scrum programs and contains the program_manager, scrum_product_owner and scrum_master roles. The plugin installs it only if Project Portfolio Management has not already done so.

Two tables hold program data. The epic_backlog_definition table stores the filter criteria for epic backlogs, and the scrum_program_m2m_group table stores the link between a program and its teams. A business rule named Set global rank for epic, in the rank_configuration table, contains a fix script that populates global rank for existing epics.

The board is controlled by the program_planning_constants UI macro, which holds two properties. TEAM_LIMIT sets how many teams the board displays and defaults to 15. STORY_LIMIT sets how many stories it displays and defaults to 1000. Raising these values can lengthen loading times and degrade board performance. Before assigning people to these roles, the roles and RACI guide for Agile Development helps you decide who holds each one.

For the other guides in this series, start from the Agile Development hub.

Frequently asked questions

Can I create a scrum program from the Agile Board?

Yes, but only for your first scrum program. Later programs need the Scrum Programs module.

Why doesn’t the planning page show my default epic backlog?

The planning page does not apply the default epic backlog automatically when you select a program. Choose the backlog from the Backlog list while you plan.

What happens to a story if I unplan it?

It depends on where you drop it. Moving it back to the team’s backlog lane clears only the sprint and keeps the assignment group. Dropping it into the epic backlog pane clears both.

Why is the planning board slow with a large program?

The board displays up to 15 teams and 1000 stories by default. Raising those limits in the program_planning_constants macro can lengthen loading. Filtering with an epic backlog limits the stories the board shows.