Scaled Agile Planning in ServiceNow: SAFe, EAP and Scrum Programs

Scaled agile planning in ServiceNow organizes several teams into one structure so features, sprints and stories line up. Three routes exist: Essential SAFe and Portfolio SAFe for the framework layers, Enterprise Agile Planning for planning intervals and sprints, and scrum programs in Agile Development 2.0 for scrum teams with a shared outcome.

Three planning models cover different levels of structure

The three models share vocabulary such as teams, release trains, iterations and backlogs, but they sit in different parts of the platform. Scrum programs are narrower. They coordinate several scrum teams toward a short-term outcome, such as a project, a release or an epic, or on ongoing work.

Planning model Suits Where it sits
Essential SAFe Teams planning on two levels Scaled Agile Framework menu, SAFe Board
Portfolio SAFe Portfolio managers grouping several release trains Scaled Agile Framework menu, SAFe Board
Enterprise Agile Planning Multi-team structures scheduled into planning intervals and sprints Strategic Planning Workspace
Scrum programs Scrum teams working toward one shared outcome Agile Development, Agile Board

Check the platform direction before choosing. Starting with the Xanadu release, the Essential SAFe and Portfolio SAFe plugins, their related content packs, the Unified Backlog plugin and the read-only roles for SAFe are being prepared for future deprecation. They will be hidden and can no longer be activated on new instances, though they continue to be supported. Enterprise Agile Planning is the newer experience for this work, so a team setting up release trains today should start there. For the wider rollout, see the Agile Development implementation roadmap.

SAFe levels run from the SAFe Board

Essential SAFe is the most basic configuration of the framework. It applies lean and agile principles to release trains and teams, aiming for fewer defects and a short lead time. Its plugin is com.snc.sdlc.safe. Product managers work at the release train level, where they keep a centralized backlog, define a program increment, pick the features to finish in it, run big room planning and follow features across a visual task board. Team members work at the team level, where they manage their backlog, streamline sprint planning and track stories between states. Program increment objectives state the goal for a team or release train inside one increment. For a plain definition of a release train, see the release train explainer.

Portfolio SAFe, installed with com.snc.sdlc.portfolio_safe, adds a top tier. Portfolio managers rank epics in a portfolio backlog, and a portfolio is a group of release trains working toward a single solution. The release train and team levels below it match Essential SAFe.

A SAFe team is created with a name, manager, group capacity in story points, group email and description, then associated with a release train by editing the release train record. Creating teams needs the admin role.

The release train backlog lists active features that are not yet assigned to a program increment. Create Feature adds a new feature at the bottom. To insert one at a specific position, select the feature just above that point first. Assigning features uses three fields: the release train, the SAFe epic and the program increment in which the features should finish.

Enterprise Agile Planning groups work by iteration

Enterprise Agile Planning backlogs group work by iteration. Team backlogs group by sprints, release train backlogs group by planning intervals, solution trains group by child release trains, and portfolios group by child solution trains. Completed and cancelled items are hidden in the Backlog section by default, while iteration sections keep showing them. Six iterations display by default, and an administrator can change that number through a system property.

Creating a planning interval

From the release train’s Backlog tab, select Create Planning interval and enter a name, a start date and an end date. From EAP version 4.17.0, those dates go straight into the modal, and matching planning calendar entries are created automatically. Turning on Create child entries on Sprint adds child sprints in the same step. If sibling release trains share the calendar and already have sprints, the child sprints match that calendar without a count or length being entered.

The role that creates iterations is sn_apw_advanced.eap_user or sn_apw_advanced.eap_scrum_master. The first iteration for teams that share a planning calendar is created by an EAP scrum master. Teams added to the release train later receive in-progress and upcoming sprints that match their siblings, though sprints that have already ended are not copied.

Sprints come from the interval

Teams usually take their sprints from the parent planning interval. A sprint is created from a team’s own backlog when the team needs a sprint outside the interval, or when the team is not yet linked to a release train calendar. Without a planning interval, the platform returns the message “Parent iteration does not exist. Create planning intervals first before creating sprints.” Create the interval first, then the sprint.

Planning across teams and methodologies

The release train planning board shows the current iteration by default. Story cards sit in sprint lanes as they were scheduled on the Backlog page. The Dependencies toggle draws links between stories, and some stories then need rescheduling. The Capacity toggle colors each sprint’s capacity bar: red for an overloaded team, grey for exactly 100 percent, and blue for less than 100 percent.
Each agile team follows either Scrum or Kanban. Scrum teams plan in sprints on their own calendar or their release train’s calendar. Kanban teams work from a continuous backlog without sprints and do not use the shared calendar. New teams default to Scrum, and when teams join a release train, the methodology is chosen once for the batch. Kanban teams have no Create Sprint button, are skipped when planning intervals or child sprints are created, and do not appear on the release train planning board.

Switching a team from Scrum to Kanban requires the sn_apw_advanced.eap_admin role. Saving the change cancels the team’s current and future sprints, while completed or cancelled sprints stay as they are. A team connected to a Collaborative Work Management board with active or planned sprints cannot be switched.

Scrum programs coordinate teams on a shared outcome

A scrum program plans and tracks several teams toward a short-term outcome, such as a demand, project, epic or release, or toward ongoing work. Teams can run different sprint cadences. A program manager with the it_program_manager role creates one under Agile Development, then Scrum Programs, then New.

Field What to enter
Planned start and end dates The program window; the start date defaults to the current day
Planned duration Calculated from the two dates; defaults to one day
Program manager The person who runs the program
Default Epic Backlog The initial backlog; it is not applied automatically, so select it during planning
Program Name A brief description of the program

Epic backlogs are sets of filters that group epics, and planning covers the stories inside the chosen backlog. Epics are created under Agile Development, then Epics, and move through the states Draft, Ready, Work in Progress, Complete and Cancelled. Each epic is associated with one product at a time. For the epic term itself, see the epic explainer.

On the program planning board, choose the program and an epic backlog, then drag story cards into sprint lanes or team lanes. Dropping a card into a team lane sets the assignment group. Dropping it into a sprint sets the sprint and the assignment group, and the sprint capacity bar fills. For the story term, see the story explainer. Dependency lines are colored by sequence. Green means the prerequisite sits in an earlier sprint, which is the intended order. Red means the dependent story is scheduled first, so the story should be rescheduled.

Keeping backlogs and sprints in order

On the SAFe Board team backlog, the program that contains the team must have an active program increment, and the Backlog tab shows the sprints of the current increment. Team backlog access requires one of the roles scrum_product_owner, scrum_master, safe_product_owner or safe_scrum_master. A sprint can start only when its increment is current, and a team can have one current sprint at a time. Completing a sprint moves its incomplete stories to the backlog or to a future sprint.

In Agile Development 2.0, the Sprint Planning tab of the Agile Board plans sprints for the assignment group chosen in the Group field. Roles that can plan include scrum_admin, scrum_master and scrum_sprint_planner. Group capacity stays editable until a sprint begins, which accounts for changes in team composition, holidays and vacations.

The Unified Backlog plugin, com.snc.sdlc.safe.multi_task, adds triage boards for records such as defects and problems. The general concept of a backlog is covered on the backlog overview page.

Frequently asked questions

Which planning model should a team on a new instance start with?

Enterprise Agile Planning is the newer experience for this kind of work. The Essential SAFe and Portfolio SAFe plugins are being prepared for deprecation and can no longer be activated on new instances, although they continue to be supported.

Can scrum teams and Kanban teams share one release train?

Yes. Each agile team carries its own planning methodology. Kanban teams are skipped when planning intervals and child sprints are created, and they do not appear on the release train planning board.

What happens to sprints when a scrum team switches to Kanban?

Current and future sprints are cancelled when the change is saved. Sprints that were already complete or cancelled are left unchanged. A team connected to a Collaborative Work Management board cannot be switched while it has active or planned sprints.

Why can’t I create a sprint from a team’s backlog?

The platform refuses the sprint when the parent release train has no planning interval. Create the planning interval for the release train first, then create the sprint.

What does a red dependency line mean on a scrum program planning board?

A red line means the dependent story is scheduled in a sprint before its prerequisite. Review the dependency and reschedule the story so the prerequisite comes first.