Create a planning interval from the EAP backlog

Create a Planning Interval from the ART’s Backlog in Enterprise Agile Planning by selecting Create Planning interval, entering a name and dates, and selecting Create. You can add child Sprints during the same action. An EAP scrum master must create the first iteration for teams sharing a planning calendar.

Prepare the planning interval in EAP Backlog

Start with the team structure, because the selected team determines the iteration you create. In the default Full Configuration, an Agile Release Train (ART) uses Planning Intervals and its Agile Teams use Sprints. Other configurations can map team levels to different calendars. Establish which ART owns the work before entering dates.

For a wider view of the hierarchy, see scaled agile planning with EAP and Scrum programs. A Planning Interval gives the ART a time window; the child Sprints give Scrum teams smaller windows within it. Creating those windows prepares the schedule, while assigning backlog items is a separate action.

Iteration creation requires sn_apw_advanced.eap_user or sn_apw_advanced.eap_scrum_master, subject to the timeline rules. The sn_apw_advanced.eap_scrum_master role creates the first iteration for teams sharing a planning calendar. Once that timeline exists, sn_apw_advanced.eap_user can create iterations following it. If creation asks you to contact a scrum master, resolve the missing timeline before continuing.

The date-entry flow described here applies from EAP version 4.17.0; check your instance and release. It creates the underlying calendar entries automatically. Existing calendar entries remain valid after an upgrade, and a matching entry makes the date fields read-only. Check the calendar arrangement before treating locked dates as a permission problem.

Create the ART interval and its child Sprints

  1. Open Workspaces > Strategic Planning Workspace > Enterprise Agile Planning.
  2. In Agile structure on the left, select the ART that needs the new interval.
  3. Open its Backlog tab and select Create Planning interval.
  4. In Create Planning Interval, fill in Name, Start date, and End date. When a matching calendar entry supplies the dates, review the displayed values.
  5. To generate child Sprints at the same time, turn on Create child entries on Sprint. Enter the number of child Sprints and the Sprint length in days when those inputs are needed.
  6. Select Create, then review the confirmation identifying the new iteration.

If sibling ARTs share the planning calendar and already have Sprints, the child Sprints follow that existing calendar. You do not supply a separate count and length in that situation. Check that the resulting cadence matches the planning conversation before moving work into it.

For associated Scrum teams, the generated Sprints align with the Planning Interval and its child spans. Kanban teams are skipped during Sprint creation and do not display Create Sprint on their Backlog. In a mixed ART, a missing Kanban Sprint is therefore expected behavior, rather than evidence that the entire creation failed.

Review one associated Scrum team after creating the ART interval. Check the Sprint dates against the parent window and compare them with a sibling team. This gives you a concrete acceptance check before a planning meeting starts filling the new iterations with work.

Check shared calendars before changing dates

By default, ARTs in an EAP configuration share planning calendars. Creating the first ART’s Planning Interval establishes dates on that calendar. Other ARTs still create their own intervals from their own Backlogs, but use the established dates. A shared calendar therefore coordinates timing without creating the other ARTs’ Planning Intervals for them.

Changing a calendar-linked iteration’s dates updates the underlying calendar entry and cascades to other iterations using it. The sn_apw_advanced.eap_scrum_master role is required to change dates on an iteration that follows a planning calendar entry. Agree the change with affected teams before editing a shared window.

An administrator can select Allow unique cadence for each team on the EAP configuration. Teams added afterward get separate calendars with corresponding calendars for their child levels. Existing teams keep their current configuration calendar. Treat this as a configuration decision, rather than a quick way to detach an interval already in use.

Review staffing separately from the iteration dates. ServiceNow resource management in PPM covers the neighboring resource-planning concern. A valid calendar window establishes when work may be scheduled; it does not establish whether the proposed workload fits the people available.

For help planning this work, see ServiceNow implementation.

Add Sprints and resolve date conflicts

To extend an existing interval’s child schedule, select the Planning Interval on the ART Backlog and use Add child sprints. Enter the count and length in the modal, then select Create. Review the resulting team Sprints. Editing a Sprint’s start date shifts its end date to preserve its length.

Use Create Sprint on an Agile Team’s Backlog when the team needs a Sprint outside the ART’s normal alignment, or is not yet linked to an ART calendar. Enter Name, Start date, and End date, then select Create. For a team under an ART, the parent Planning Interval must exist first; a missing parent produces an error directing you to create Planning Intervals.

  • Planning Intervals on the same ART cannot overlap.
  • Sprints for the same team under the same parent Planning Interval cannot overlap.
  • Child Sprint dates must remain inside their parent Planning Interval.
  • Adjacent iterations can follow one another without a gap.
  • Shortening or moving a Planning Interval fails if existing child Sprints would fall outside its revised dates.

When resolving a conflict, inspect both the proposed window and the existing iterations. Changing the name does not resolve an overlap. For broader decisions about operating cadence and dependencies, see IT strategy planning.

Populate the interval and make it visible

Creating team work items requires sn_apw_advanced.eap_user. Select the team, then use New <work item type> in the page header. Available types depend on the team configuration; More options can expose another type. Complete the form and select Submit. Check where the item appears because its entered values determine its Backlog section.

Scheduling work also requires sn_apw_advanced.eap_user. Locate an item in Backlog, use its more icon or right-click menu, and choose an existing iteration. Story points can be entered inline during grooming. The same menu lets you reschedule an item to another iteration or return it to Backlog.

Use Move to top or Move to bottom to rank stories, features, capabilities, or epics within their current list. If the list is grouped, remove the grouping first, because reordering is not possible while items are grouped. Ranking and scheduling solve different problems: moving an item to the top changes its position, while choosing an iteration changes its scheduling destination. Review both before the team treats the plan as agreed.

If the new interval seems absent, inspect the view before creating another one. Use the column filter icon to narrow rows by any choice, string, or reference column, and use the column choice option to decide which columns the Backlog displays. By default, the ART Backlog groups work by Planning Interval. You can also group by a column, but items cannot be reordered while they are grouped.

The Backlog displays six iterations per EAP Team by default. Changing that limit requires sn_apw_advanced.eap_admin and the Strategic Planning application scope. In sys_properties.list, select New, set Suffix to sn_apw_advanced.eap_backlog_iterations_limit, choose Integer for Type, enter the desired maximum as Value, and select Submit. A display limit is separate from iteration creation.

Before handing the interval to team members, record its name, parent ART, date range, and expected child Sprints in your planning notes. Compare those details with the created records so that a display filter or a similarly named interval does not send the team to the wrong schedule.

Questions about interval handoffs and exceptions

What happens when a Scrum team joins the ART later?

From EAP version 4.17.0, a team that joins the ART later receives the in-progress Sprint and the upcoming Sprints matching its siblings. Ended Sprints are not copied. If sibling teams have no Sprints, there are none to generate for the joining team.

Can a canceled interval’s dates be reused?

Canceled iterations do not reserve their dates. You can create an iteration with the same dates as a canceled one. Complete iterations do reserve theirs and cannot be overlapped. Complete iterations also retain their historical dates when changes cascade through a shared calendar.

Does copying a work item put it in the new interval?

Create copy requires sn_apw_advanced.eap_user and copies required-field information into a new item in the original’s section. A copy made in Backlog remains there, so review its details and scheduling destination before including it in the new plan.

What must happen before completing a Planning Interval?

The start and completion action requires sn_cwm.cwm_user. Complete child Sprints first. Open overlapping child Sprints trigger an alert identifying the teams and Sprints to close. Teams connected to CWM start or complete their Sprints from the CWM Board instead.

Can the next interval start while the current one remains open?

A team can have one current iteration at a time. Complete its current iteration before starting the next. If incomplete work remains at completion, choose whether to move it to Backlog or a future iteration.