To create a work order plan in ServiceNow, open Enterprise Asset Workspace, start a plan from Work management or an asset group, and complete the playbook. Define the assets and task template, confirm scope, assign groups and technicians, review the schedule, then release the tasks for work and track progress.
Prepare the assets and sequence before creating the plan
A work order plan brings related asset tasks into one managed sequence. A shutdown, safety inspection, calibration, condition assessment, and restart can belong to the same plan. This gives the asset manager a place to review the affected equipment and coordinate the people and timing around the work.
Creating and managing the plan requires sn_eam.asset_manager. Before creating it, the Apply Work Order template in draft status setting must be enabled in the Field Service Configuration module. Check these instructions against your instance and release.Before opening the form, decide which asset or asset group is the main target, which other assets belong in scope, and which work order template contains the required tasks. Think through the operating sequence with the maintenance owner. A restart task needs a clear handoff from the preceding inspection; putting both task names in a plan does not explain what the technician must check.
For the broader maintenance context, see enterprise asset maintenance work orders. Keep this plan focused on a defined set of asset work with an identifiable completion point.
Create a work order plan from the workspace
There are two starting routes. Use the first when you want to select the scope while building the plan. Use the second when you have already identified an asset group.
- Navigate to Workspaces > Enterprise Asset Workspace > Work management.
- Open Work order plans and select New.
- In Create work order plan, optionally choose a Work order plan template.
- Enter the Plan name, then select OK.
Alternatively, navigate to Workspaces > Enterprise Asset Workspace > Enterprise asset estate, open Asset groups, select the group, and select Create plan. When starting from an asset group, the template selection shows the work order plan templates associated with that group.
If you choose a template, Plan name starts with its name and can be changed. Give the resulting plan a name that distinguishes this execution from the reusable pattern. For example, describe the equipment and purpose rather than leaving several active plans with indistinguishable names.
The Work order plan playbook begins with activities in Pending status. Its sequence is Details, Review affected assets, Review work order tasks, and Track status. Review work order tasks contains Review assignments and Review schedule.
Complete Details and verify the affected assets
On Details, Name, Location, Primary target, and Work order template are required. Primary target identifies the asset or asset group. Work order template defines the collection of tasks for the assets in scope. Additional assets extends that scope, while Due date records when the plan must be completed.
Use Description to explain the purpose and boundaries of the work. A maintenance coordinator should be able to understand the intended outcome without guessing why the equipment appears in the plan. If a particular inspection determines whether the restart should proceed, make that decision clear in the work instructions rather than relying on the plan name.
Selecting Location first filters Primary target and Additional assets to assets at that location. If the expected asset is missing, review that location choice before assuming the asset record is absent. A template populates Description, Location, Primary target, Work order template, and Additional assets; review those values for this execution.
Select Update to save while continuing to edit, or Mark complete to save and advance. In Review affected assets, inspect the actual asset list. Select an asset and Remove if it should be excluded, then select Mark complete when the scope is correct. Treat this review as a check of the work boundary, especially when a group contains equipment that should stay operational.
Assign responsibility before arranging the schedule
In Review assignments, set Assignment group for each work order task. You can select multiple tasks before choosing a group when the same team will handle them. All work order tasks need an assignment group before this activity can be completed.
Assigned to is optional, but it affects scheduling. The schedule is populated in Review schedule when a technician is specified, and tasks need a technician to appear in the calendar. A group assignment establishes team responsibility; a named technician is what lets a task appear on that person’s calendar during scheduling.Review handoffs between teams before selecting Mark complete. For a shutdown and restart sequence, ask who confirms that the equipment is ready for the next operation. This is a planning check: do not assume a team assignment communicates the acceptance criteria to the next technician.
If the work depends on a separate purchasing issue, track that dependency explicitly. Procurement case management and tasks covers the adjacent coordination topic.Review timing before selecting Ready for work
In Review schedule, inline edit Scheduled start to schedule a task manually. Estimated end is populated from Estimated work duration. Check the duration as well as the start: a plausible starting time can still produce a finish that misses the plan’s Due date.
For technician-assigned tasks, select Calendar view. You can adjust scheduled start and estimated end by dragging the task edges, reposition the task, and double-click it to open its record. The calendar also displays active tasks from other work orders, maintenance plans, incidents, and ad hoc work orders, giving the scheduler context beyond this plan.
Compare the calendar with the intended operating sequence. Check that preparation finishes before the work needing it, that inspections have time allocated, and that restart does not overlap work requiring the asset to remain shut down. These are coordination checks; do not infer an automatic dependency rule from the way tasks appear on a calendar.
Select Ready for work when the assignments and timing are ready for execution. After this action, scheduled start and end times cannot be modified. Review them before releasing the work, then select Mark complete to advance to Track status.
For help planning this work, see ServiceNow implementation.
Track execution and preserve a repeatable starting point
The sn_eam.asset_technician role receives assigned tasks and completes them through the Mobile Agent application. In Track status, State, Actual work start, and Actual work end update based on technician actions. Use those actual times to distinguish work that has started from work that was merely scheduled.
The Track status calendar shows tasks in Work in progress; completed tasks do not appear there. Use the associated plan to review task status rather than interpreting an empty calendar as proof that no tasks existed. When work spans teams, review the task records around handoffs so a completed activity is understood in context.
For repeat work, sn_eam.asset_manager can create a template through Work management > Work order plan templates > New, complete its fields, and select Save. Primary target is required. Choosing an asset group adds its assets to Affected assets, and Additional assets must share the primary target’s location. Details also provides Save as template for saving a plan configuration.
Keep procurement timing separate from execution evidence. Where replacement equipment must arrive before a shutdown, review the relevant purchase requisition and purchase order states before treating the plan’s planned dates as achievable.
Questions about work order plan design choices
Should two similar shutdowns share one plan?
Consider whether they share an operational boundary and completion decision. If one can finish while the other remains unresolved, separate plans may make responsibility clearer. Similar task names alone are a weak reason to combine different work windows.
How detailed should a plan description be?
Include the intended result, equipment boundary, and reason for coordinating the tasks. Keep task-specific execution instructions with the work they describe. The description should help a reviewer decide whether the plan covers the right job without becoming a second task list.
What should a coordinator discuss when a technician changes?
Discuss completed preparation, outstanding checks, and the condition in which the equipment was left. A new technician needs context for the next action. Treat that conversation as an operational handoff rather than assuming the assignment field explains the work already performed.
When is a reusable template worth creating?
Consider one when the asset scope and task pattern recur with limited variation. If each execution needs substantial redesign, first clarify the common pattern. A template should provide a dependable starting point that the manager can review for the next job.