A ServiceNow change approval policy is a record that tells a change workflow which user and group approvals a change request needs. The policy holds decisions, and each matching decision points to an approval definition. A Change Approval Policy workflow activity applies the policy to a change request and returns an outcome such as Approved, Rejected or Skipped.
How a change approval policy decides what approval is needed
The policy does not check approvals in isolation. It evaluates the current change request together with any extra inputs supplied to it, then picks out the decisions whose conditions match. Each matching decision brings in its approval definition, and the definition generates the user or group approval that the change needs before it can move on.
A single workflow can hold several Change Approval Policy activities. Each activity can reference the same or a different policy. The activity is available only when the workflow runs on a table that extends or is the Change Request table.
Each decision has its own condition; the variable inputs decide which decisions match, and each matching decision applies its approval definition. For the wider change request states, see the change request lifecycle states guide.
Building the policy from approval definitions
Approval definitions are the building blocks. They are created under All, then Change, then Change Policy, then Approval Definitions. Selecting New opens the form, and the name comes first. The role needed to create one is change_manager or admin. For how roles are granted across the instance, see instance security and access control.
A definition controls several things at once. It decides whether the approval is user based or group based. It decides whether the approval can approve or reject automatically on a user’s behalf. It decides whether a response is required. Four settings need particular care:
| Setting | What it controls | Why it matters |
|---|---|---|
| Mandatory checkbox | Whether the change approval policy must wait for a response from the generated approval | A mandatory approval holds the policy open until someone answers |
| Approval action | The type of approval record the definition creates | Sets the type of approval record the definition creates (Approve, Reject, user approval or group approval) |
| User or group basis | Whether one named person or a whole group is asked | For a group approval, Wait for sets whether the first response, all responses or a percentage of members must respond. |
| Automatic response | Whether the definition can approve or reject on a user’s behalf | Whether the definition can approve or reject automatically on a user’s behalf |
A policy can contain several decisions. When a decision’s condition matches, its related approval definition is evaluated. For how standard changes are modeled, see the standard change template guide.
Applying the policy inside a flow
A policy can also be applied from a flow with the Apply Change Approval Policy flow action, alongside the workflow activity described above. The action is added inside Workflow Studio. The path is All, then Process Automation, then Flow Designer, then Flows. Open the flow you want to change, then choose Action, then Installed Spokes, then ITSM, then Change, then Apply Change Approval Policy. The role required is admin.
The form has four inputs:
- Action Label, a unique name for this step in the flow.
- Policy, the Change Approval Policy to apply.
- Change Request, the source record required by the policy.
- Due Date, which sets what happens if no one responds in time. The options are None, Approve, Reject and Cancel. Approve, Reject and Cancel act automatically on the due date.
The action applies the selected policy to the change request.
Reading the outcomes of the Change Approval Policy activity
The activity has three inputs. Approval Policy names the policy to apply. Policy Input passes additional values, but each input has to be defined on the policy record first. Finish condition decides whether the activity can complete while approvals are still pending.
The activity can return five results: Approved, Rejected, Canceled, Skipped and Finished. The transitions that follow from them are:
| Transition | When it fires |
|---|---|
| Approved | The criteria of the applied approval definitions are met |
| Rejected | Any rejection from an applied approval definition |
| Error | The event or condition that generates an error. |
| Skipped | The activity finishes as skipped, with the fallback described below |
The Skipped row has a detail that is easy to miss. If the Skipped condition is not configured on the activity, the Approved condition is used instead. A skipped result can therefore continue down the approval path unless the Skipped transition has been set up on purpose. Anyone building a workflow should decide that intentionally rather than leave the default in place.
The activity also moves through five states: Executing while the engine runs its logic, Waiting while it ignores the activity until an event restarts it, Finished once it completes, Cancelled when the activity or its containing workflow is canceled, and Error when a JavaScript error occurs. When an error appears, the logs hold the error details.
Pausing approvals when a change is put on hold
A change can be put on hold partway through the approval cycle, and the policy has to handle that. When the change request goes on hold and the Finish condition is set, the activity completes and the workflow disregards pending approvals until the change request resumes. When the hold is released, the activity restarts.
A Normal change workflow can include an activity that checks whether the group manager has approved the change. That check reads a policy input, which has to be defined on the Change Approval Policy record before the activity can use it. For the related change board tooling, see the CAB workbench page.
Where approval records are stored and how requests are raised
Approvals raised by a flow use the Ask for Approval action. Its inputs are Record, Table, Approval Reason, Approval Field, Journal Field, Rules and Due Date. The table you select must support approvals by having an approval state field. The Approval Reason is a text justification kept for audit and compliance. The Approval Field holds the result, and the Journal Field stores the history and comments.
Approval rules decide how many responses count and in what way. The options are Anyone approves, All users approve, All responded and anyone approves, a percentage of users approve, and a number of users approve. Approvers can be individual users, groups, values taken from a field on the record, or people added by hand to the Approvers related list.
Rejection needs its own rule set. Define rejection rules by adding another OR rule set, and include them so the flow does not sit in a waiting state indefinitely. For approval controls on requests rather than changes, see the request approval controls article.
Individual approvals are recorded in the sysapproval_approver table. Each approval moves through a set of states: Not Yet Requested, Requested, Approved, Rejected, Cancelled, No Longer Required and Skipped. The Approval State output is a choice field with those values, and it appears in the Data panel.
By default, approval records are generated for inactive users and groups. The system property com.glide.hub.flow.approval.allow_inactive_entity changes that behavior. Before changing it, review which approvers the flow is actually reaching.
Workflow Studio does not support making multiple approval requests to the same record; asking for approval on the same record from different branches creates a dependency between them.
Configuration points to check before publishing a policy
Several of the points above are easy to overlook. Set the Mandatory checkbox on each definition deliberately, because it decides whether the policy waits. Define each policy input on the policy record before a workflow references it. Configure the Skipped transition explicitly on each activity so a skipped result does not fall through to Approved by accident. Define rejection rules as a separate OR rule set alongside the approval rules. Keep the parallel-branch restriction in mind when designing a flow that handles several approvers at once.
How do DevOps change policies decide between automatic approval, rejection and manual review, and why must deployment permissions stay a separate control?
As of November 2026, a DevOps change policy can read pipeline evidence such as test results, code coverage and incident counts, and compares it with thresholds the team has set. Clear passes are approved, clear failures rejected, and the rest goes to a person. Deployment permissions stay separate because an approval means little if one identity can push to production.
What the policy looks at before it decides
A policy is only as reliable as its inputs. The usual ones are test status, coverage and open incidents on the affected service. Each should arrive from the pipeline or the incident record, not from someone typing it in. If a test stage was skipped or a coverage report never arrived, the policy has no reliable signal, so the case goes to manual review.
How each of the three outcomes is reached
- Automatic approval can be set to require every input to meet a threshold agreed in advance, such as all tests passing, coverage holding steady and no open incident on the target service.
- Rejection follows a hard failure, such as a failing test stage. In most implementations the rejection should name the failed input so the developer knows what to fix.
- Manual review covers borderline results, missing evidence and sensitive services. It is the default for any case the rules do not clearly cover.
How to turn automation on safely
- Record the current flow first, including how many changes wait for approval and how many later cause an incident.
- Keep human approval in place while the policy runs, and log what it would have decided.
- Compare its decisions with reviewer decisions over a fixed period and adjust thresholds where they disagree.
- Enable automatic approval for the lowest-risk services first, and make missing or stale evidence route to manual review.
Why deployment permissions stay a separate control
An approval record shows that a decision was made, not that the change reached production through the approved path. If one identity can edit thresholds, change a pipeline gate and deploy, the approval becomes a formality that identity can route around. Production access controls can be enforced outside the ticketing workflow where needed.
What to check in a DevOps change setup
- Which identities can deploy to production, and whether any of them can also approve changes or edit policy.
- Whether the pipeline can deploy without a linked change request, since that path skips the policy entirely.
- What the policy does when a test stage is skipped, times out or reports stale results.
- Which automatic approvals were later tied to an incident or rollback, reviewed on a fixed schedule.
Frequently asked questions
What is a change approval policy in ServiceNow?
It is a policy record that holds decisions. Each decision that matches a change request brings in an approval definition, and that definition generates the user or group approval the change needs.
Which role is needed to apply a change approval policy in a flow?
The Apply Change Approval Policy flow action requires the admin role. Creating approval definitions requires the change_manager or admin role.
What does the Skipped outcome mean?
It is one of the results the activity can finish with. If the Skipped condition is not configured on the activity, the Approved condition is used, so the workflow continues down the approval path.
What happens to pending approvals when a change goes on hold?
With the Finish condition set, the activity completes and the workflow disregards pending approvals until the change request resumes; the activity restarts when the hold is released.
Where are individual approval records stored?
They are stored in the sysapproval_approver table. Approval results go to the Approval Field on the record, and history and comments go to the Journal Field.
What does the Mandatory checkbox do on an approval definition?
It determines whether the change approval policy must wait for a response from the approval generated by that definition.