A ServiceNow unauthorized change request is an emergency-type record that Change Management opens when a configuration item changes without an approved change covering it. It opens in the Review state, not Scheduled, because the change has already been implemented. The reviewer can select Request Approval, which sends it back through Authorize for sign-off, and once it is approved a post-implementation review follows.
How an unplanned change reaches Change Management
Change Management learns about an unplanned change through the Service Mapping integration with ITSM. When Service Mapping detects unauthorized activity on a configuration item (CI), the Change Management application receives an event notification, and an emergency unauthorized change request is created for that CI. The reviewer can then approve or reject the change from inside that application.
Discovery adds a second input. Horizontal or top-down discovery can record a change to a CI property that is not a real change, because of a measurement error or because the same value is written differently, such as with different letter case. The filtering described below exists to keep those readings out of the queue.
Which configuration items are in scope
Requests are created for CIs that belong to application services, and they are not created for CIs outside those services. The Unauthorized Change Properties page also lets an administrator choose the CI classes to monitor, and a monitored CI must itself belong to an application service. Email notifications follow the same boundary. They are sent for an unplanned change on a CI in an application service, whether that service was discovered or entered manually.
How false positives are filtered out
The filter is a flapper algorithm that applies a learning pattern. When a CI property tied to a service changes, the system writes the new CI and field value pair to a flapper data table. A nightly job then runs several algorithms over that data to find patterns that point to false positives.
Where the strategy predicates for the changed fields predict, at a confidence above 90 percent, that all of the new values are false positives, the change is ignored and the learning model stays as it is. That step is skipped for a CI linked to an active change request.
The aim is to report real changes. Triggering recomputation and timeline updates is a significant step, and an emergency change request is treated as a critical action, so keeping false positives out protects both.
The checks that decide whether a request opens
When an unplanned CI change occurs, the system works through a fixed sequence of checks:
- The CI must belong to an allowed CI class.
- If the CI was flagged before, and that earlier unauthorized change falls inside the notification ignore period, the system takes no further action.
- Otherwise, the system looks for a change request that matches the configured conditions and is linked to the CI. If one is linked, the change is not flagged.
- If none is linked, the change is flagged as unauthorized and a ci.change.unplanned event is raised.
The notification ignore period defaults to one day in the Australia release. During that period, notifications and new unauthorized changes are suppressed for the same CI.
Turning request creation on and off
Flagging a change and creating a request are separate steps. When the ci.change.unplanned event arrives, the system checks the Enable event processing setting, and a request is created when that setting is true. The setting defaults to false in the Australia release.
A Change Management property, com.snc.change_request.enable_unauthorized, also governs creation. It accepts true or false and defaults to false in the Brazil, Xanadu and Yokohama releases. Administrators reach the Change Management properties through Change > Administration > Change Properties.
Many CI changes at once, with no open change request covering them, produce a request for each CI and a large number of notification emails. To stop that during a batch of updates, an admin or change manager goes to All > Change > Administration > Unauthorized Change Properties, clears the Enable event processing check box, and selects Update. Creation stops, and no notifications are sent. The setting has to be switched back on when the updates are finished, because while it stays off no unauthorized change requests are created.
What the request contains when it opens
The form arrives partly filled in. The Unauthorized option is selected, which marks the record as an unauthorized change. The Assignment group is set to Change Management. The Configuration item field holds the CI that changed. The Description field lists the changed CI fields along with their new values, and working out how the change came about is left to the review.
Why the request skips Schedule and Implement
A standard or normal change is planned before any work begins. An unauthorized change is different, because the implementation has already happened when the request opens. The request therefore enters the Review state directly and skips the Schedule and Implement states. The reviewer examines a change that has already taken effect and works back toward its cause.
Approval leads to a post-implementation review
Selecting Request Approval moves the request back to Authorize for sign-off. Once it is approved, the request returns to Review, and the system creates a post-implementation review change task. That task carries the short description Post Implementation Review, has State Review, and is assigned to the Change Management group. Members who receive the notification can work through the task and close it. The review exists to judge the risk and impact of a change that went ahead without approval.
Converting the request into an emergency change
A change manager can clear the Unauthorized check box to turn the request into an emergency change request. The reason for the change goes into the Work notes field. ITIL users have a different route. They clear the Unauthorized check box by creating an outage from the task record and setting the Type field to Outage.
If an unauthorized change has no outage record attached, the flow moves from Authorize to Review and skips the Schedule and Implement states, because the implementation has already happened.
How the change types compare
Change Management recognises three ITIL change types, and the change model, which has superseded the type field, decides the state model and the approval path. The table below sets the three types side by side.
| Change type | Pre-approved | CAB authorization required | Typical use |
|---|---|---|---|
| Standard | Yes | No | Routine, repeatable work where the outcome is already well known |
| Normal | No | Yes | Any change that is neither pre-approved nor an emergency and needs a full assessment before it goes ahead |
| Emergency | No | Yes | High-priority work, such as resolving a major incident or applying a security patch |
A standard change follows a specified procedure, and approved standard changes can be predefined as catalog templates, so group-level, peer and CAB steps are not required. A routine TLS certificate renewal is typically handled this way. An emergency change bypasses group and peer review and goes straight to Authorize for CAB approval. A normal change needs assessment, peer or technical approval, and CAB authorization before implementation.
If an unplanned CI change happens while an emergency change is in progress, an unauthorized change request is created and sent for approvals.
The change states these requests move through
Each type moves through states in its own order. A normal change passes through New, Assess, Authorize, Scheduled, Implement, Review and Closed. A standard change goes from New straight to Scheduled. An emergency change skips Assess but still needs Authorize before it can be scheduled.
A change can be canceled from any state except Review and Closed. Cancel is unavailable while a change sits in Review, so an unauthorized request, which opens in Review, cannot be canceled until it has moved on. The requester receives an email when a change reaches Scheduled, Implement, Review or Canceled.
A normal change can be reverted to New from Assess, and an emergency change from Authorized, using the Revert to New action. That action cancels pending approvals and restarts the workflow.
Frequently asked questions
Why did a change not produce a request?
The CI has to belong to an allowed CI class and to an application service. A CI flagged recently, inside the notification ignore period, does not receive a new request. A change linked to a matching change request is not flagged in the first place.
Does a flagged change create a request on its own?
Not by default. The ci.change.unplanned event leads to a request when the Enable event processing setting is true, and that setting is false by default in the Australia release.
Why does the request open in Review?
The change has already been implemented when the request is created. The request therefore skips the Schedule and Implement states and enters Review, where the reviewer assesses a change that has already happened.
How do I stop the notification emails?
Clear the Enable event processing check box on the Unauthorized Change Properties page and select Update. Request creation stops, and no notifications are sent. Switch the setting back on when the batch of updates is finished, so that real unplanned changes are flagged again.