Technology Lifecycle Management (TLM): Timelines, Risk and Audit

Technology Lifecycle Management (TLM) shows when the software and hardware under business applications reach end of support, end of extended support and end of life. It draws those dates as Gantt timelines, rolls a risk level up from products to services to applications, and flags audit exceptions where a date was estimated or missing, inside the Enterprise Architecture Workspace.

What TLM tracks and why the dates matter

The software and hardware beneath a business application have a shelf life. Operating systems, database engines, development tools and middleware each move through support stages, and a vendor can stop supporting a version while the application still depends on it.

TLM builds an inventory of the technologies in use. For each product it keeps the version, the manufacturer’s support dates, an internal lifecycle guideline, the risk of staying on an ageing version, and a retirement date that can be planned alongside the application it supports. The inventory also feeds upgrade planning.

The feature was previously called Technology Portfolio Management (TPM), and table and job names still use TPM. TLM labels appear when the Enterprise Architecture Workspace application is version 9.2.1 or later and the Technology Lifecycle Management plugin (sn_apm_tpm) is version 1.11.0 or later.

How technologies link to business applications

The chain starts with the Consumes and Consumed by relationship, which must point to an Application Service that has been mapped. Each service then yields its computers. The Software Installations tab on each computer shows its installed software, and any attached hardware model appears under the TLM Discovered Technologies tab.

Software aligns properly when its discovery model has a product type of Licensable or Unknown and the model has been normalized. Each qualifying discovery model produces one TLM Discovered Technology record. That record creates a TLM Technology Lifecycles record, fetches the lifecycle information, and receives a unique TLM lifecycle record identifier.

When a product is missing from a timeline, check this table first.

Data needed Source tables
Business application Business Application
Application service Service Instance, linked through the Service CI Association table
Hardware Computer, with the Hardware Model reference populated
Software Software Installation, Software Discovery Model, Software Product and Software Product Lifecycle

By default, software is read from the Computer table and its similar instances, plus the Docker Container and Serverless Hardware tables. Software held in another CMDB table can be added through the sn_apm_tpm.configurationItemsWithSoftwareInstalls system property, as a comma-delimited list. Software lifecycle data appears when the Software Asset Management (SAM) Foundation or SAM Professional plugin is installed.

Lifecycle timelines on the Gantt chart

The Gantt view arranges business applications at the top, their application services beneath them, and the hardware models and software products beneath those. Each bar represents a lifecycle with up to three phases: end of support, end of extended support and end of life. Pointing at a bar shows its phase details. A software product is identified by its name, version and edition together, so each combination gets its own lifecycle record.

How end dates are worked out

Each phase ends on the day the next phase begins. Take a product with an end of support start date of 1 December 2023 and an end of extended support start date of 30 December 2023. The end of support phase finishes on 30 December 2023, even though no end date was entered for it.

A product with a single phase still needs a finish point for its bar. The engine adds the period set in the sn_apm.endRangeofTPMLifecycle system property to the current date. With a three-year value and a run on 1 December 2023, the phase would end on 1 December 2026. That end date is calculated, not taken from the lifecycle data, so read it with that in mind.

Rolling dates up to services and applications

A service bar starts at the earliest phase start among the software products and hardware models it runs on. A business application bar starts at the earliest start among its services. If service A runs a software product with end of support on 1 December 2023 and a hardware model with end of support on 15 December 2023, the service bar starts on 1 December 2023.

Risk scores and how they roll up

Risk is worked out for each software model and each hardware model before anything is rolled up. A software model is assessed on four inputs: internal lifecycle stage, external (publisher) lifecycle stage, internal age and external age. A hardware model uses four matching inputs.

Stage risk comes from the software product lifecycle form, where a risk level is attached to each lifecycle phase. The levels run from none through low and moderate to high and very high, and each organization sets them to match its own tolerance. Aging risk uses these bands: 0 to 90 days counts as high, 90 to 180 days as moderate, and more than 180 days as low. The aging calculation is scripted and can be edited.

The same logic then moves up the chain.

Level Model Application service Business application
High A single high input makes the model high A high hardware or software model makes the service high A high service, or a high model underneath, makes the application high
Moderate A single moderate input makes the model moderate The service is moderate when its highest model is moderate The application is moderate when its highest service is moderate
Low The model is low when all inputs are low The service is low when all models under it are low The application is low when all models under it are low

The business application figure draws on its production application services.

Watching risk over time

Run the Populate Technology Lifecycle Risks scheduled job to refresh the figures. The View all technology lifecycle risks link on the workspace home page lists risks by earliest lifecycle date. It looks 1, 3, 6, 12 or 18 months ahead, defaulting to 1 month.

The technology portfolio view and its tabs

The Technology Portfolio page holds the TLM work alongside the Technology Reference Model (TRM) catalog. Open it from the Technology Portfolio icon in the workspace. Its five tabs are TRM catalog, Technical Debt, Technology lifecycles, TLM risk and Technology portfolio audit. Three of them carry the lifecycle picture.

Tab What it shows
Technology lifecycles Lifecycle timelines for software and hardware, plus the TRM product and lifecycle that govern each software record’s obsolescence status
TLM risk Risk data for software products facing high or moderate technology risk
Technology portfolio audit Lifecycle entries where a date was approximated, not found, or does not exist

For the workspace layout, start with the Enterprise Architecture Workspace overview. The IT asset lifecycle management guide covers purchased IT assets, a different subject.

Audit exceptions and verification

The audit tab lists lifecycles that were approximated, not found, or missing for a software product or hardware model. The audit matters because version numbers do not always match the lifecycle catalog exactly. A product recorded as full version 9.2.1 may have an end of support entry for version 9.2 instead, and the audit shows that gap so the team can find the exact match.

A user with the sn_apm.apm_user role settles each exception by setting its Verification Status to Verified or Rejected on the exception form. Verified reduces the exception count in the Technology Lifecycle table. Rejected also reduces the count, and the dates for that phase stop appearing.

Running and recovering the data jobs

The main job is Populate TPM Discovered Technologies and Lifecycles. An admin finds it under System Definition, then Scheduled Jobs, and selects Execute Now. It stores lifecycle values in the TPM Technology Lifecycle table, and run status appears under Setup, then Logs, in the workspace.

To refresh one business application, open its record in the Portfolio List view and choose Update TLM Data from the three-dot menu. An on-demand job starts for that record, and the sn_apm.apm_user role is enough to run it.

If the job is interrupted, the Restart button on the run log page becomes active one hour after the log stops updating. Restarting resumes from where the job stopped. Watch the Records Processed field: if the count of TLM discovered technologies stops rising during a run, the job may have stalled.

Records created before plugin version 1.9.0 have no lifecycle record identifier. Run the Populate Number field in TPM Discovered Technologies job, with the application scope set to Technology Lifecycle Management, to fill them in.

Software filtering is the last adjustment. TLM tracks licensable software by default. To include non-licensable products, copy an encoded query from the Software Installations list filter into the sn_apm_tpm.softwareDiscoveryModelProductFilterForTPM system property, then run the population job. An example reads [discovery_model.norm_product.product_type=child].

Frequently asked questions

Is TLM a different feature from TPM?

No. TLM is the current name for the same feature, and table and job names still say TPM.

Why do my screens still say TPM?

The Enterprise Architecture Workspace application must be version 9.2.1 or later, and the Technology Lifecycle Management plugin must be version 1.11.0 or later. If either is older, the TPM wording stays.

Why is a software product missing from the timeline?

Check its discovery model. It needs a Licensable or Unknown product type and must be normalized. Non-licensable software is excluded by default, and software lifecycle data requires the SAM Foundation or SAM Professional plugin.

What changes when an exception is verified or rejected?

Both statuses reduce the exception count in the Technology Lifecycle table. Rejected also stops that phase’s dates from appearing, so the timeline no longer shows them.