Alignment Planner workspace: planning and aligning work items

The Alignment Planner Workspace in ServiceNow Strategic Portfolio Management connects planning items, such as projects, demands and epics, to the goals and targets they support. This guide covers which records can be linked, the routes for making each link, how a primary goal differs from a regular relationship, and what the app’s recent releases changed.

Which records can be linked to a goal

Planning items are the work records the workspace plans, prioritises and places on roadmaps. Project, Demand and Epic are the planning item types available by default, and each can be linked to a goal or target without extra setup.

Other ServiceNow AI Platform table records can also be linked. Those links are filed under a separate tab on the goal record. A custom planning item type is handled more strictly: it can be linked from the Align work window only after its table is added to a system property, and the same rule applies when a custom planning item is given a primary goal.

Two routes for linking work to a goal

The Align work window handles several planning items in one action, which suits a batch of projects that support the same goal. The Planning items tab on a goal or target handles one planning item at a time through a relationship form.

Route Items per action Other table records Where the link is listed
Strategy and Goals page, Align work window Several Yes, through the Other item option Aligned work tab on the goal record
Portfolio plan, Align work window Several No, planning items only Planning items tab on the goal record
Goal record, Planning items or Other items tab One Yes, through the Other items tab Planning items tab or Other items tab

The route used determines which tab a link lands on, so a reviewer who checks only one tab can miss links made through another route.

Aligning work from the Strategy and Goals page

This route starts from the goal list rather than a single plan. It needs the sn_apw_advanced.spw_goal_user role.

  1. Open Workspaces, then Strategic Planning Workspace, then Strategy and Goals.
  2. Select the goal-based board that holds the goal or target.
  3. Open the row context menu for that goal or target and choose Align work.
  4. In the Align work window, choose Planning item or Other item. Pick the records, use the Name column filter to narrow a long list, and select Confirm.

Linked records then appear on the Aligned work tab of the goal record.

Aligning planning items from a portfolio plan

Inside a portfolio plan, the Goals view lists the goals and targets of that plan on its List tab. The Align work window in this route handles planning items only.

  1. Open Workspaces, then Strategic Planning Workspace, then Portfolio Planning.
  2. Select the portfolio plan that contains the goal.
  3. In the Goals view, open the List tab.
  4. Open the row context menu for the goal or target and select Align work. Alternatively, select View aligned work and then the Align work icon on the side panel.
  5. In the Align work window, select the planning items and choose Confirm.

Adding one relationship from the goal record

This route suits a single item, or a planner who prefers to complete a form. It is also how a non-planning record is linked through the Other items tab.

  1. Follow steps 1 to 3 of the portfolio plan route, then select the goal or target. The side panel opens on its Details tab.
  2. Select Full Details to open the goal form.
  3. On the Planning items tab for a planning item, or the Other items tab for any other record, select Add.
  4. On the Goal/Target Relationship form, enter the Planning item type and Planning item, or the Table and Document ID for other records.
  5. Select Done or Save.

Planning item relationships name the sn_align_core.apw_user role alongside sn_apw_advanced.spw_goal_user. The form’s Primary field makes the new relationship primary and fills in the Primary goal and Primary target fields on the planning item.

How a primary goal differs from a goal relationship

A work item can name one primary goal and one primary target in fields on the record itself. Additional goals and targets are added through the Goal/Target Relationships related list on the same form, and they hold a secondary association.

  • The first goal or target linked to a planning item becomes its primary by default.
  • A later link is secondary unless the Primary field is selected when it is added.
  • Making a different goal primary turns the existing primary into a secondary association.
  • If the item holds both, make another goal primary before removing the primary one.
  • Entering a target in the Primary target field fills in the Primary goal from that target’s goal.
  • Strategic items such as initiatives and strategic programs do not support a primary goal or target.

Required plugin and role for each record type

The plugin and role for a primary goal depend on the record type. Check this table before setting one. For the wider roles across the process, see the roles, responsibilities and RACI guide.

Work record Plugin Role
Project PPM Standard project_manager
Demand PPM Standard demand_manager
Program PPM Standard program_manager
Feature Agile Development 2.0 rm_feature_admin
SAFe Feature Scaled Agile Framework safe_art_user or safe_admin
Scrum Epic Agile Development 2.0 scrum_story_creator
SAFe Epic Scaled Agile Framework safe_art_user
Planning item (Project, Demand, Scrum or SAFe Epic) Strategic Planning sn_align_core.apw_user

Custom planning item types and the allow lists

Two system properties control custom types. The property sn_align_core.planning_item_types_allow_list covers portfolio plans, and sn_align_ws.freeform_planning_items_creation_list covers free-form roadmaps. Changing them requires the sn_align_core.apw_admin role.

Open All, then System Properties, then All Properties, and open the property. Add the table name in the Value field, for example sn_align_core_custom_planning_item_1, and select Update. For portfolio plans, the type then goes into the lens planning managers use. For free-form roadmaps, planning items are created from the roadmap view.

A custom planning item table left off the list cannot be linked from the Align work window.

Goal and target fields to know

The Goal form generates a GOAL number automatically, with a prefix an administrator can change. Its status is Red, Yellow, Green or None, and its progress is calculated when it has sub-goals or targets. Start and end dates default to the current quarter, and a sub-goal takes its parent’s dates.

On the Target form, a Maximize target calculates progress as (Actual minus Base) divided by (Target minus Base), times 100. A Minimize target reverses the base and actual terms. Maintain-type targets measure the share of breakdown periods that meet their plan.

Deleting a goal also deletes its targets and their progress records, even when the Allow the deletion of targets property is set to No. Duplicating a goal or target opens a copy named Copy of followed by the original name.

Reviewing aligned work and check-ins

The Goal insights skill is on by default and needs the sn_apw_advanced.spw_goal_user role. Only the owner or contributors of a goal can generate its insights. The skill reads the goal, its targets, its sub-goals and its aligned work, then reports a forecasted status, targets at risk, delayed or stalled aligned work, and recommendations.

The forecasted status is the worst status among targets and sub-goals, and aligned work does not change it. For the wider governance model around these reviews, see the governance model guide. Before a manual regeneration, check the timestamp on the insights card, because regenerating without a reason raises token consumption.

For check-ins, the Send reminder option on a target’s row menu notifies contributors to update the target actuals before the due date.

Release history of the Alignment Planner Workspace

The releases below include changes that touch planning items, goals or related records.

Version Month Change relevant to alignment
8.15.0 June 2026 Planning Item lens for planning without an organisation structure, programs, portfolios or products; public portfolio plans shared through a copied link
8.17.0 August 2026 RIDAC tracking for planning items, with role-based access
8.18.0 September 2026 Dedicated RIDAC page for portfolio risks, issues, decisions, actions and changes
8.19.0 October 2026 Unique identifier column in the goals grid of a portfolio plan
8.20.0 November 2026 Record History tab hidden on substate and WIP limits table forms

The app is named Alignment Planner Workspace, while instance menus read Strategic Planning Workspace and Portfolio Planning. Use the menu names when following the steps above.

Frequently asked questions

Which records are planning items by default?

Project, Demand and Epic. Any other planning item type, including a custom one, needs its table added to the planning item types allow list property before it can be linked from the Align work window.

Why use the Planning items tab instead of the Align work window?

The Align work window links several planning items in one action. The Planning items tab adds one at a time through the Goal/Target Relationship form, which suits a single change.

Which roles are needed to align work with a goal?

The Strategy and Goals route needs sn_apw_advanced.spw_goal_user. Planning item relationships also name sn_align_core.apw_user.

How is a primary goal different from a goal relationship?

A primary goal sits in a field on the work record. A goal relationship is added through the Goal/Target Relationships related list and remains secondary unless the Primary field is selected.

Does linking work change a goal’s status?

No. Aligned work does not change the goal’s status, which is the worst status among its targets and sub-goals.

The Strategic Portfolio Management guides on this site cover the wider planning and goal topics.