A portfolio plan in ServiceNow Strategic Planning Workspace is built by one planning manager from a lens and a filtered set of planning items, with goals defined afterwards. It is created in a four-step wizard, shared at viewer or editor level, and governed through a RIDAC page that gathers the risks, issues, decisions, actions and changes raised against its work.
What a portfolio plan holds
A portfolio plan is a custom plan that one planning manager owns. The manager sets goals, puts a target against each goal and roadmaps the work so planned work lines up with those goals. One manager can keep several plans, each built through a different lens. A strategy leader using the Strategic Investments lens sees the plan by initiative, while a department head using the Organization lens sees it by department. The lens sets the perspective the plan is built from: the Strategic Investments lens plans by initiative and the Organization lens plans by department.
Planning happens across the Prioritization, Roadmap, Kanban and Hierarchy tabs. The Hierarchy view traces how strategy breaks down, so an initiative can be opened to reveal the epics beneath it and the goals it supports. For the broader picture, see the plain-language guide to strategic portfolio management.
High-level plans use strategic item types. The main ones are:
| Item type | What it represents in a high-level plan |
|---|---|
| Initiative | A long-term goal meant to create a lasting competitive edge, often spanning several departments |
| Strategic program | The milestones and outcomes that move one initiative forward |
| Program (pm_program) | The milestones and outcomes of a program |
By default, initiatives and strategic programs come from the Strategic Investments lens, and programs from the Project Program lens.
Choosing a lens and the entity behind it
The first three wizard choices decide what lands in the plan. The lens sets the perspective. The entity type sets the level you plan at, and you then select entities of that type. With the Organization lens and Department as the entity type, choosing HR limits the plan to work tied to that department. Next comes the planning item type, such as Project, plus optional conditions that combine into a filter. The Business Capability lens also requires the Enterprise Architecture Workspace to be installed and the sn_apm.apm_user role.
Building the plan through the four-step wizard
Open Strategic Planning Workspace, go to Portfolio Planning and select New. The user needs the sn_align_core.apw_user or business_stakeholder role. The wizard then runs in four steps:
- Select a lens.
- Choose an entity type and the entities of that type.
- Select the planning item type and add any conditions.
- Enter the name, owner, start and end dates and description, pick a scoring framework, and select Create.
A custom scoring framework can be set up from the Explore scoring frameworks option.
The start and end dates also filter what enters the plan. A planning item enters the plan when its approved start or end date falls inside the plan timeline, or when it does not have both approved dates. When a project is missing, check its approved dates first. A demand converted into a project in Project Portfolio Management appears as the project rather than the demand.
Sharing, duplicating and keeping access tidy
Share a plan from the Share portfolio plan icon in the header. The Copy link option gives a direct route to the plan, but it opens the plan just for people who already hold the right role. Recipients are added in the Members or Groups field, given Viewer or Editor access, and notified by email.
Viewers can comment and add attachments but cannot change the plan’s settings or data. Editors can change both. Read access comes from the sn_align_core.ap_read_only role and edit access from sn_align_core.apw_user. A user with the edit role but viewer-level sharing cannot edit planning items from the grid or side panel, though the record page stays open to them. For how the wider roles fit together, see the roles, responsibilities and RACI guide for strategic portfolio management.
Shared users see the Prioritization, Roadmap, Kanban and Hierarchy tabs by default. Capacity needs sn_align_ws.spw_capacity_user or sn_align_ws.spw_capacity_read, Financials needs sn_align_ws.spw_financial_user, and Goals needs sn_apw_advanced.spw_goal_user.
Duplicate portfolio plan, under More actions, copies the Goals, Prioritization and Roadmap data and keeps dependencies among the copied items. The default name adds “(Copy)” to the original, and an option carries over the original users and groups. Plans shared at view or edit level can be duplicated too. Editing or deleting a plan sits in the same menu, and deletion asks for confirmation.
Saved views for each stakeholder
A view saves one way of looking at the plan: which columns appear, how items are grouped and which filters apply. The display choices carry across the Prioritization, Roadmap, Capacity and Financials tabs. Each plan allows three private views and ten shared views. Views work in the Planning module in live mode and are not supported in scenario mode.
To create one, adjust the plan, select Save as new view in the header, name it, and turn on the Shared view toggle if stakeholders should see it. Deleting a view removes it and its saved changes, while the projects, demands and epics stay in the plan. The view owner or a plan editor can delete a view, which frees a slot when the limit is reached.
Tracking governance with RIDAC
RIDAC stands for Risk, Issue, Decision, Action and Change. A risk is a potential event that could hurt a planning item. An issue is a current blocker. A decision is a choice or approval needed to move the item forward. An action is a task that addresses a risk or issue or carries out a decision. A change is a modification to scope, schedule, resources or another attribute.
To create a RIDAC item, a user with the sn_align_core.apw_user role opens the plan’s Planning page, selects an item in Prioritization, Hierarchy or Roadmap, opens its full details, chooses the Risks, Issues, Decisions, Actions or Request Changes tab, selects New and saves. The item then appears on the plan’s RIDAC page. That page gathers RIDAC items for the demands, projects, epics, capabilities, features, initiatives, strategic programs and goals inside the plan, which lets a portfolio manager spot cross-project risks and dependencies without opening each project’s menus.
The wider RIDAC home page has four tabs:
| Tab | What it shows |
|---|---|
| All RIDAC | Accessible items across projects and demands |
| Project RIDAC | Items created on project planning items |
| Portfolio RIDAC | Risks and issues whose top-level parent is a portfolio |
| Program RIDAC | Risks and issues whose top-level parent is a program |
Each user sees the items their access allows. Read access uses sn_align_ws.ridac_read_only and edit access uses sn_align_ws.ridac_user. Filtered lists export to Excel, PDF, CSV or JSON.
With integration enabled, RIDAC links planning items and execution tasks in both directions, so a record created on either side shows the details from the other. Portfolio Planning covers projects and demands. Strategic Planning adds epics, capabilities, features, initiatives, strategic programs, goals and more, along with AI-generated RIDAC capabilities.
Administrators run one standing job. It populates the planning item field on RIDAC records created before Portfolio Planning Workspace was installed, so those records appear correctly in related lists and reports. For the wider governance context, see the governance model for strategic portfolio management.
Strategic program records and their fields
The strategic program form has four groups. The core group holds the name, state, parent initiative, owner, percent complete, MoSCoW priority and work notes. MoSCoW runs from 1 Must have through 2 Should have and 3 Could have to 4 Won’t have. The details group covers approved and actual dates, priority and linked business capabilities and applications. The business case group holds the overview, background, limitations, approach and benefits. The financials group sets planned cost, capital and operating expenditure and benefit beside their actual counterparts, plus planned return on investment, so gaps are easy to spot.
Reading portfolio insights
Portfolio insights in the plan header produce AI-generated insights. The generative AI skill is on by default and requires sn_align_core.apw_user. The insights cover delayed planning items, date misalignment between planned and approved dates, delayed starts, projects at risk that show early warning signs without having slipped yet, and budget overrun where the current fiscal year forecast exceeds the approved budget. Insights are grouped as critical, medium or low. Each opens a root cause analysis, which can reveal compounding problems such as one resource overallocated across several items, followed by recommended actions. Regenerate or Refresh rebuilds the insights from the latest data.
Frequently asked questions
Why is an approved project missing from my portfolio plan?
Check the plan’s start and end dates first. An item enters when its approved dates fall inside the plan’s timeline, or when it does not have both approved dates. If the project came from a demand converted in Project Portfolio Management, the plan shows the project in place of the demand.
What is the practical difference between a viewer and an editor?
A viewer can comment and add attachments but cannot change the plan’s settings or data. An editor can change both. Viewer-level sharing also blocks edits from the grid and side panel, even for a user holding the apw_user role, though that user can still edit from the record page.
Who can see the RIDAC page for a plan?
The page lists RIDAC items attached to the planning items and goals in the plan, and each user sees the items their access allows. Creating a RIDAC item needs the sn_align_core.apw_user role. Read access to the RIDAC home page uses sn_align_ws.ridac_read_only, and edit access uses sn_align_ws.ridac_user.
What happens to the projects if I delete a portfolio view?
The view and its saved changes are removed. The projects, demands and epics stay in the plan. Deleting the plan itself also deletes its views.