Goal Framework for Strategic Portfolio Management measures a goal through its targets. Each target has a type that sets how achievement is worked out, a progress value that feeds the goal, and a Green, Yellow or Red status. Status is recalculated when actual values change, then moves upward through breakdowns, targets and parent goals.
How goals, targets and strategic plans fit together
Strategic priorities sit inside strategic plans, and goals are defined under those priorities. A goal then needs one or more targets, which hold the measurable part of the work: a start value, a final target value and the actual value reported so far.
Goal Framework for Strategic Portfolio Management extends the base Goal Framework. Installing the extension keeps the base features and adds target automation, which fills in actual values from a data source.
Choosing a target type
The target type decides how achievement is measured. Ask what the metric should do over time.
| Target type | Typical use | How achievement is judged |
|---|---|---|
| Maximize | Growing a metric such as revenue | Progress rises as the actual value moves from the start value toward the final target value |
| Minimize | Reducing a metric such as costs | Progress rises as the actual value falls from the start value toward the final target value |
| Maintain above | Holding a floor, such as uptime | A period is met when its actual value is at or above its planned target |
| Maintain below | Holding a cap, such as operating costs | A period is met when its actual value is at or below its planned target |
| Maintain constant | Keeping a level steady, such as headcount | A period is met when its actual value sits inside a tolerance band |
| Milestone | Yes or no outcomes, such as a go-live | Yes is Green and No is Red; there is no Yellow status |
For Maximize, the achievement percentage is the actual value minus the start value, divided by the final target minus the start value, multiplied by 100. A revenue goal starting at 1,000,000 with a final target of 1,500,000 and an actual of 1,350,000 gives 70 percent, which is Red. Minimize reverses the subtraction so that a drop counts as progress. A cost goal starting at 500,000 with a final target of 400,000 and an actual of 420,000 gives 80 percent, which is Yellow.
The Maintain constant tolerance is built from the planned target. The range runs from the planned target minus the tolerance share of its absolute value, up to the planned target plus that same share. The default tolerance is 5 percent, which administrators can change through the sn_gf.maintain_constant_tolerance_percent system property.
For the Maintain types, the planned target of each breakdown equals the final target value. The actuals to date figure is the value for the latest period, not a running sum. Progress stays empty until a period has an actual value.
Changing the type of a target that already holds actuals can ask for confirmation. The prompt appears when the change clears or resets those values. Moving between two Maintain types keeps the actuals and recalculates progress. Moving between Maximize, Minimize and a Maintain type clears the actual value and progress. Moving to Milestone deletes the breakdowns.
How status is calculated and rolled up
Status is calculated when actual values are entered. The default thresholds are Green at 90 percent or higher, Yellow from 75 to 89 percent, and Red below 75 percent. An administrator can change these through the sn_gfa.target.auto_status.thresholds system property.
Target owners can override the calculated status for a breakdown, a target or a goal. A later change to the actual value recalculates it, and custom status values are kept when automatic calculation is switched back on.
Status then moves up in three steps: breakdowns into the target, targets into the goal, and goals into any parent goal. The last two steps use worst-wins logic, so a single Red target can surface at the top of the portfolio.
With cumulative breakdowns, the latest period decides the target status. Consider an annual revenue target with quarterly check-ins. Q1 reaches 88 percent and is Yellow, while Q2, Q3 and Q4 reach 96 percent, 94.7 percent and 96.8 percent, each Green. The target shows Green, because Q4 is the latest reported period.
With non-cumulative breakdowns, the target status comes from the combined window across all reported periods. Suppose each quarter has a planned 250,000 and the actuals are 220,000, 240,000, 200,000 and 230,000. Q4 on its own reaches 92 percent and shows Green. The window across the four quarters is 890,000 against 1,000,000, or 89 percent, so the target shows Yellow.
Maintain targets use the share of periods met. Take a floor of 99.5 percent on API uptime, checked quarterly. Q1 meets it, so progress is 100 percent. Q2 misses it and progress falls to 50 percent, which is Red. Q3 and Q4 both meet the floor, which brings progress to 75 percent by Q4, a Yellow result.
How progress reaches the goal
A goal with targets and no sub-goals takes the sum of its target progress values and divides by the number of targets. When sub-goals are present, the sum runs across sub-goals and targets together, using the Impact on parent goal field for sub-goals and the Impact on goal field for targets.
When the sn_gf.weighted_average_enabled property is set to Yes, the result becomes a weighted average. Take a goal with two targets. Target 1 has an impact of 2 and stands at 40 percent, so it contributes 2/5 of 40, which is 16 percent. Target 2 has an impact of 3 and stands at 20 percent, so it contributes 3/5 of 20, which is 12 percent. The goal progress is 28 percent.
Recording progress and creating targets
Creating a target needs the sn_gf.goal_user or sn_gf.goal_admin role, and the goal’s owner or contributors are the people who add targets to it. A target can be created from the goal’s Quantitative or Qualitative Targets related list, or from the Targets module. For Maintain targets it is how performance is tracked across periods.
Progress records are created when the target is saved after the Actuals to date field has a value. Deleting a goal also deletes its targets and their progress records, even when the property that allows target deletion is set to No.
For a target without automation, the owner updates Actuals to date, adds a business justification in the Remark field, and selects Update. For an automated target, the Target form offers an Update Actual value related link. Progress for the target and its goal then recalculates.
Check-in breakdowns and the goal calendar
Check-in frequency creates breakdowns automatically. The options are Daily, Weekly, Monthly, Quarterly, Yearly and, in fiscal mode, Period.
With the split-equally option, each breakdown’s planned value is the final target divided by the number of breakdowns, and the actuals entered in each breakdown are summed. For 1,200 new customers across 2025 on a monthly check-in, that means twelve breakdowns of 100 each. With the spread-linearly option, the planned values rise so that the last breakdown equals the final target. The application then reads the latest breakdown’s actual alone, so the owner enters a running total.
The goal calendar, set for the whole instance, decides which periods breakdowns use. The default is Gregorian. Fiscal mode uses one of three fiscal types: Regular, 445 (4-4-5), or 13 Period. Changing the calendar mode or fiscal type, regenerating or deleting fiscal periods, or choosing an unsupported frequency can make a target with breakdowns stale. Targets set to None, targets on the legacy fortnightly frequency and milestones never become stale.
Recovering stale targets
A stale target has its value and structure locked, and it has two routes back.
The first is the scheduled job named Goal calendar alignment, Reset check-in frequency for stale targets. It needs the sn_gf.goal_admin role and runs on demand. The administrator sets a start date and an end date in YYYY-MM-DD format, and may add an encoded query. The job processes targets whose start date falls on or after the start date and whose end date falls on or before the end date. Clearing the check-in frequency deletes the existing breakdowns but keeps the total actuals. The owner then selects a frequency again, and the breakdowns are rebuilt to match the calendar.
The second is to duplicate the target and set a frequency on the copy, which does not carry remarks, work notes or history.
Frequently asked questions
Which target type fits a cost cap?
Maintain below suits a cap. A period is met when its actual value is at or below the planned target.
Why can a target show Yellow when its latest period is Green?
That happens with non-cumulative breakdowns. The target status comes from the combined window across all reported periods, so an early shortfall can hold the overall figure in Yellow.
What changes when I switch a target’s type?
Between two Maintain types the actuals stay. Moving between Maximize, Minimize and a Maintain type clears the actual value and progress. Moving to Milestone deletes the breakdowns.
Can I override a calculated status?
Yes. A target owner can set a status manually for a breakdown, target or goal, and a later change to the actual value recalculates it.
Why is my target locked?
The target is probably stale. A calendar change, a fiscal type change or regenerated fiscal periods can leave a target’s breakdowns out of step with the goal calendar. An administrator can run the reset job, or the owner can duplicate the target.