Plan an audit engagement with advanced planning

Advanced planning is an option on the audit engagement form. It creates an engagement project in the background, and resource and cost plans then attach to the engagement. Start from All > Audit > Engagements > Create New, then use Validate and Plan, then Enable Advanced Planning, to generate the project.

What advanced planning changes on an engagement

A standard engagement record holds the dates, people, description and results for one piece of audit work. Advanced planning adds a planning layer to that record. Once the engagement project exists, the engagement shows a Resource Plan related list and a Cost Plan related list. You then add a resource plan and a cost plan, and their values roll up to the engagement and to the audit plan it belongs to.

That roll-up is the main reason to set the feature up early. On the form, the planned figures come from the plans, so the numbers on the engagement reflect the plans you built rather than estimates typed in separately.

Prerequisites: plugins and the Validate and Plan button

Advanced planning depends on a set of store applications and plugins. Confirm that each one is active before you open the engagement form:

  • GRC Advanced Audit plugin (com.sn_audit_advanced)
  • GRC Profiles
  • GRC Policy and Compliance Management
  • GRC Risk Management
  • GRC Advanced Core
  • GRC Advanced Risk
  • GRC Audit Management
  • Project Portfolio Management Standard

The Validate and Plan button appears when the Advanced Audit plugin is activated. If the button is missing from the form, check that plugin first. The engagement also has a Parent plan field, which names the plan the engagement is associated with.

Before you commit to the plugin set, review the audit management licensing and cost factors, so the decision is made with the cost side in view.

Create the engagement and generate its project

The procedure requires the sn_audit.manager role. Work through these steps on the engagement form:

  1. Go to All > Audit > Engagements > Create New.
  2. Enter the Number, which is the unique identification number of the engagement, and the Name.
  3. Choose a Type. The list includes None, Internal Audit, External Audit, SOX Audit, IT Audit, Financial Audit and Compliance Audit, along with other audit types such as Vendor Audit and Project Audit.
  4. Set Assigned to, Auditors and Approvers. Assigned to names the user on the engagement. Auditors and Approvers list the people assigned to the work and to approving it.
  5. Enter the Description and Objectives, which record the general purpose and the stated objectives of the engagement.
  6. Set the schedule fields, including Engagement planned start, Engagement starts and Fieldwork planned start.
  7. Click Validate and Plan. The project details populate on the form.
  8. Click Enable Advanced Planning. An engagement project is created in the background, and the Resource Plan and Cost Plan related lists appear.

For help planning this work, see ServiceNow implementation.

Run the two project buttons in the order shown. Enable Advanced Planning can also run later, on an engagement that is in the Validate or Fieldwork state.

When the Project field fills in

The Project field holds the engagement project. The field is populated when you click Validate and Plan. It is also populated when you click Enable Advanced Planning on the engagement in the Validate or Fieldwork state. The field can fill in without either click when the engagement is already linked to a plan with advanced planning capabilities, when the user has the required roles, or when the engagement is in the correct state.

If the Project field stays empty after the buttons run, check the plan link, your role and the engagement state against those three conditions on your instance.

Engagement form fields that the plans drive

Several fields on the form take their values from plans, timecards and audit tasks, so the numbers change as you add those records.

Schedule and fieldwork fields

Fieldwork planned duration takes a number of days and hours. Together with the Fieldwork planned start, it is used to calculate the planned end. Use the planned end date the form calculates, and check it against the dates your fieldwork plan uses.

When audit tasks exist, Fieldwork planned duration is set to the longest planned duration among those tasks. Fieldwork actual start takes the earliest actual start among the tasks, and Fieldwork actual end takes the latest actual end. Fieldwork actual duration is the span between those two actual dates. Set the task dates before you review the fieldwork figures, so the engagement does not show dates that disagree with the tasks.

The Engagement starts and Engagement ends choices let the form set those dates automatically, based on the state you select. Engagement starts can follow the Scope, Validate or Fieldwork state. Engagement ends can follow the Follow Up or Closed state. Engagement planned start and Engagement planned end hold the estimates, while Engagement actual start and Engagement actual end hold the real dates.

Expense and resource fields

Planned expenses shows the estimated expenses from the cost plan once a cost plan is defined. Planned resources shows the estimated hours from the resource plans once those are defined. Actual expenses and Actual resources are set from timecards once timecards are defined, so they start to move after time is recorded against the engagement.

Budgeted expenses and Budgeted resources, in hours, are the targets for the engagement. Set them on the form before you build the plans.

Link the engagement to its audit plan

The Parent plan field sets the plan that the engagement is associated with. Because resource and cost values roll up to the audit plan, the parent link determines where those totals land. Set it when you create the engagement, not after the plans are built, so you do not have to trace totals back to a different plan later.

After you save the first resource plan, open the audit plan and check that the engagement’s planned resources appear in its totals. If they do not, check the parent link before you add more plans.

Build the resource and cost plans

Once the engagement project exists, the next two steps are creating a resource plan and creating a cost plan. The resource plan drives the Planned resources figure on the engagement, and the cost plan drives Planned expenses. Typically, build both before the engagement moves into Fieldwork, so the comparison with budget is complete when fieldwork starts.

After you save each plan, reopen the engagement and check Planned expenses and Planned resources. The numbers should match the plan totals. If they do not, confirm that the plan is linked to this engagement and not to a different record.

Use the gap between budget and plan as the first review point. Compare Budgeted expenses with Planned expenses, and Budgeted resources with Planned resources. A difference in either direction is worth a line in Work notes, so the reason for the gap stays with the engagement.

Engagement states, comments and results

The State field runs through Scope, Validate, Fieldwork, Awaiting Approval, Follow Up, Closed Complete and Closed Incomplete. Percent complete records how far the engagement has progressed. Change the state as each phase of the work ends, and update Percent complete as fieldwork moves forward.

For more on state transitions, read the page on the audit engagement lifecycle.

The engagement has two comment fields. Additional comments are viewable by customers. Work notes are viewable by the administrator and the audit manager. Write internal reasoning in Work notes, and use Additional comments for text the customer should read.

When the work is complete, set Result to Satisfactory, Adequate or Inadequate and record the justification in Opinion. Before you set the result, confirm that the evidence supporting it has been collected. For how requests for that evidence are handled during fieldwork, see audit engagement evidence requests.

Setup problems and how to check them

Setup problems usually trace back to a small number of causes. Check these first:

  • Validate and Plan is missing. Check that the Advanced Audit plugin is activated.
  • The Project field is empty. Check the plan link, your role and the engagement state.
  • The Resource Plan and Cost Plan lists are missing. Those lists appear after Enable Advanced Planning runs, so run that step first.
  • Fieldwork dates differ from the tasks. Check the task dates, because the fieldwork fields draw from them.

When setup is complete, the next page to read covers creating control tests from an audit engagement.

Questions about report output, access, approvals and budget

What do the Knowledge base and Report template fields do?

The Knowledge base field identifies the knowledge base you use to select the report template. The Report template field holds the template that generates the knowledge base article reporting the engagement results. The KB article field shows the knowledge base article that was generated recently and contains those results.

Who can open an engagement marked as confidential?

Setting the Confidential option limits access to the record. Access is restricted to the assigned confidential users or confidential groups of users. Other users cannot open the record, so confirm the assignments before you flag the engagement.

Who has to approve time cards when several people are listed?

The Time card approver field names the person assigned to the engagement, and you can change that person. If you select more than one user, everyone on the list must approve the time cards.

How is Remaining budgeted expenses calculated?

Remaining budgeted expenses is the difference between Budgeted expenses and Planned expenses. The form sets the value automatically, so adjust the budget or the cost plan rather than the remaining figure itself.