To perform PI planning in Enterprise Agile Planning, use the Planning board to coordinate stories across teams and sprints, inspect dependencies, and compare planned work with capacity. Select the ART and Planning Interval, review scheduled work, resolve sequencing and workload issues, then track progress as teams deliver the plan.
Prepare the ART before you perform PI planning
PI planning needs a shared view of which teams will do the work and when that work can happen. In EAP, the ART provides the cross-team context. Its child teams have their own sprints, while the ART can use a Planning Interval as its calendar. Agree on this structure before the planning meeting so participants discuss the same time horizon.
The role required for planning work for an ART is sn_apw_advanced.eap_user. For this procedure, open Workspaces > Strategic Planning Workspace > Enterprise Agile Planning. In Agile structure on the left, choose the ART and select Planning Board. The board initially shows the ART’s current iteration. Select another iteration when the meeting concerns a different interval.
Before moving cards, have the participating teams identify the intended PI and review their sprint boundaries. A story placed in an unexpected sprint can be a calendar misunderstanding rather than a disagreement about priority. Keep organizational design questions separate from scheduling decisions; the related guide to scaled agile planning across SAFe, EAP, and Scrum programs helps frame that choice.
Check the configuration and labels on your instance and release before the session. The groupings below describe EAP’s default Full Configuration; enabled work item types, team hierarchy, and planning calendars affect what participants see.
Read the board at the right planning level
An ART’s story view organizes cards by child team horizontally and by the child teams’ iterations vertically. When the ART uses a PI calendar, those vertical lanes represent sprints within the selected PI. This lets participants examine a team’s proposed sequence and compare it with work belonging to other teams in the same interval.
The board changes meaning at other levels. An Agile Team uses a simpler Kanban layout with story states as vertical lanes for the selected iteration. A Solution Train groups work horizontally by child ART, while a Portfolio groups it by child Solution Train; their vertical lanes represent item state. Read the lane headings before interpreting a card’s position as a schedule commitment.
Work item visibility also depends on configuration. An ART with Full Configuration shows Features by default. Viewing other types, such as Stories, Capabilities, or Epics, requires the corresponding EAP configuration. Work with your admin when the type needed for planning is unavailable. Treat a missing type as a configuration check before treating it as missing work.
Use compact cards when scanning short descriptions across a large plan. Switch to full size cards when reviewing item Number, State, and indicators such as enabler, dependencies, or blocked. The broader Agile Development use cases for enterprise teams can help connect this planning view with the surrounding delivery process.
Turn the initial schedule into a team agreement
Story cards appear in Sprint lanes according to scheduling already performed on the Backlog page. Start by reviewing that existing placement with the teams. Ask whether the assigned team can perform the work, whether the sprint is the intended one, and whether another story must happen first. This makes the initial board a proposal to validate rather than a plan participants accept without discussion.
- Select the ART iteration that the group intends to plan.
- Review the story placement across the child teams’ Sprint lanes.
- Open a story card in the side panel when its details need discussion.
- Update priority, story points, or blocked reason as the teams agree on changes.
- Drag a card to another Sprint lane to reschedule it, or to another team’s lane to reassign it.
Make reassignment explicit during the meeting. Moving a story to a different team’s lane changes the ownership discussion as well as the board’s appearance. Ask the receiving team to review its workload and the story’s assumptions before proceeding to the next item. After a sprint move, revisit dependencies because the revised timing may affect another team’s planned work.
The side panel supports shared discussion without leaving the planning context. Use its Attachments tab for files and its Comments tab for notes and mentions of team members. Select Full details when the discussion needs additional story information, such as scrum tasks. For a separate Scrum program workflow, see Scrum programs setup and task planning.
Resolve dependencies alongside sprint capacity
Enable Dependencies to inspect relationships between stories. Review dependent work with both teams present so a scheduling change reflects the prerequisite as well as the downstream need. A board can show a plausible workload for each team while still containing a sequence that cannot support delivery.
Enable Capacity to see the teams’ workload for each Sprint. The capacity bar provides three signals: red means the team is overloaded, grey means it is at 100% capacity, and blue means it is below 100%. Use the signal to decide which stories need closer discussion; the team still needs to assess the work behind the estimate.
For example, suppose one team has an overloaded sprint and another story depends on its work. Moving the prerequisite later might reduce the first team’s load while creating a new timing problem downstream. Review the connected stories together, agree on their revised placement, then inspect the receiving sprint’s capacity. This avoids solving one visible issue by moving it elsewhere in the plan.
For help planning this work, see ServiceNow implementation.
Investigate gaps before accepting the plan
An empty lane or missing card deserves a targeted check. First confirm the selected ART and iteration. Then check the work item type being displayed and whether the relevant type is enabled. Finally, compare the expected story’s team and sprint assignment with the board context. Keep these checks separate so an apparent scheduling problem does not lead to unnecessary record changes.
The ART Planning board does not display child Agile Teams that use the Kanban planning methodology because those teams do not use iterations. A dismissible message indicates that some teams may be absent. Account for those teams in the planning discussion rather than assuming the visible sprint lanes represent the complete ART.
Two configuration issues can explain cards disappearing from a view. For custom story states used as vertical lanes, state bucket mappings in the rm_story dictionary are required; otherwise, those cards can disappear after a reload. When an ART first switches from Story to another configured type, check that the Vertical lane selection in the Planning board personalization is not set to Enterprise agile iteration..
Continue reviewing the plan during delivery
Close the planning session with a review of unresolved dependencies, overloaded sprints, and blocked stories. Give each unresolved decision a named participant and a follow-up discussion. The board shows the work, but only the teams can decide what to do about it. Before the session ends, record each open decision with one named owner and the date the team will revisit it.
Return to the board when priorities, assignments, or timing change. Review the affected story, reschedule or reassign it as needed, and inspect the resulting dependencies and capacity. For assigned and scheduled work, EAP dashboards support progress tracking at different levels of the Agile structure. Use that wider view to connect team delivery with the ART’s planning discussion.
Questions about PI planning board choices
Is the SAFe PI planning board interchangeable with the EAP Planning board?
They are distinct planning experiences. The SAFe board has controls such as the Stories and Features toggle, SAFe PI selector, and Feature Backlog pane. Identify the board you are using before applying a sequence of controls from another workflow.
Can EAP create work items from the Planning board?
Yes. The Planning board supports creating work items of multiple types and changing the Type displayed, as Backlog does. Agree on the required work item type before creating records during a shared planning session.
How does a Kanban Portfolio board handle work without a child-team assignment?
Its assigned work appears in a two-dimensional board with teams horizontally and work states vertically. Work that has no child-team assignment appears in the Portfolio section, giving the planning discussion a place to review unresolved ownership.
Does a colored SAFe dependency mean the story is complete?
No. On the SAFe PI planning board, dependency colors describe scheduling order: green places the prerequisite in an earlier sprint, yellow in the same sprint, and red in a later sprint. Story completion has a separate card indicator.